Overall Project Status

Status Date Overall Project Status Project Officer Contact
26 Jun 2024 57 % pipes supplied (62888m various dia pipes out of 110112m). 28.07% pipe laying completed (30016.10m pipes out of 106916m) Vadanappilly AE
12 Jun 2024 57 % pipes supplied (62888m various dia pipes out of 110112m). 22.027% pipe laying completed (29824.1m pipes out of 106916m) Vadanappilly AE
27 Apr 2024 57 % pipes supplied (62888m various dia pipes out of 110112m). 22.027% pipe laying completed (23551.1m pipes out of 106916m). Vadanappilly AE
18 Apr 2024 57 % pipes supplied (62888m various dia pipes out of 110112m). 19.736% pipe laying completed (21101.1m pipes out of 106916m). Vadanappilly AE
08 Apr 2024 57 % pipes supplied (62888m various dia pipes out of 110112m). 15.914% pipe laying completed (17015.1m pipes out of 106916m). Vadanappilly AE
19 Mar 2024 57 % pipes supplied (62888m various dia pipes out of 110112m). 7.936% pipe laying completed (8485.8m pipes out of 106916m). Vadanappilly AE
16 Mar 2024 57 % pipes supplied (62888m various dia pipes out of 110112m). 7.29% pipe laying completed (7801.8m pipes out of 106916m). Nattika AEE
14 Mar 2024 57 % pipes supplied (62888m various dia pipes out of 110112m). 7.29% pipe laying completed (7801.8m pipes out of 106916m). Vadanappilly AE
29 Feb 2024 57 % pipes supplied (62888m various dia pipes out of 110112m). 5.129% pipe laying completed (5484.4m pipes out of 106916m). Vadanappilly AE
21 Feb 2024 57 % pipes supplied (62888m various dia pipes out of 110112m). 2.27% pipe laying completed (2434m pipes out of 106916m). Vadanappilly AE