Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
14 Feb 2024 | 57 % pipes supplied (62888m various dia pipes out of 110112m). 2.27% pipe laying completed (2434m pipes out of 106916m). | Vadanappilly AE | |
06 Feb 2024 | 57 % pipes supplied (62888m various dia pipes out of 110112m). 1.32% pipe laying completed (1453m pipes out of 106916m). | Vadanappilly AE | |
22 Jan 2024 | 57 % pipes supplied.(62888m various dia pipes out of 110112m | Vadanappilly AE | |
22 Jan 2024 | 57 % pipes supplied.(62888m various dia pipes out of 110112m) | Vadanappilly AE | |
18 Jan 2024 | 57 % pipes supplied.(62888m various dia pipes out of 110112m) | Vadanappilly AE | |
08 Jan 2024 | 57 % pipes supplied.(62888m various dia pipes out of 110112m) | Vadanappilly AE | |
03 Jan 2024 | 57 % pipes supplied.(62888m various dia pipes out of 110112m) | Vadanappilly AE | |
28 Dec 2023 | 57 % pipes supplied.(62888m various dia pipes out of 110112m) | Vadanappilly AE | |
23 Dec 2023 | 57 % pipes supplied.(62888m various dia pipes out of 110112m) | Vadanappilly AE | |
16 Dec 2023 | 57 % pipes supplied.(62888m various dia pipes out of 110112m) | Vadanappilly AE |