| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 20 Jul 2022 | Estimate returned with incorporating road reformation estimate- The revised estimate submitted | Perlassery Sn 2 AE | |
| 17 Jul 2022 | Estimate returned with incorporating road reformation estimate- The revised estimate submitted | Perlassery Sn 2 AE | |
| 11 Jul 2022 | Estimate returned with incorporating road reformation estimate- The revised estimate subhmitted | Perlassery Sn 2 AE | |
| 08 Jul 2022 | Estimate returned with incorporating road reformation estimate- The revised estimate under preparation | Perlassery Sn 2 AE | |
| 04 Jul 2022 | Estimate returned with incorporating road reformation estimate- The revised estimate under preparation | Perlassery Sn 2 AE | |
| 30 Jun 2022 | Estimate returned with incorporating road reformation estimate- The revised estimate under preparation | Perlassery Sn 2 AE | |
| 26 Jun 2022 | No response even in the extended due dates.To be re-tendered | Perlassery Sn 2 AE | |
| 22 Jun 2022 | No response even in the extended due dates.To be re-tendered | Perlassery Sn 2 AE | |
| 15 Jun 2022 | No response even in the extended due dates.To be re-tendered. | Perlassery Sn 2 AE | |
| 12 Jun 2022 | No response even in the extended due dates.To be re-tendered. | Perlassery Sn 2 AE |