| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 09 Jun 2022 | No response even in the extended due dates.To be re-tendered. | Perlassery Sn 2 AE | |
| 04 Jun 2022 | No response even in the extended due dates.To be re-tendered. | Perlassery Sn 2 AE | |
| 30 May 2022 | No response even in the extended due dates.To be re-tendered. | Perlassery Sn 2 AE | |
| 06 May 2022 | Due to no response tender due date extended to 09.05.22 | Kannur PH Dn EE | |
| 16 Apr 2022 | Work tendered. Due date 18.04.2022 | Kannur PH Dn EE | |
| 04 Mar 2022 | TS Issued and Tender process started | Kannur PH Dn EE | |
| 19 Feb 2022 | Submitted to SE, PHC Kannur for TS | Kannur PH Dn EE | |
| 07 Jan 2022 | Submitted to SE, PHC Kannur for TS | Kannur PH Dn EE | |
| 06 Jan 2022 | Estimate submitted for approval | Perlassery Sn 2 AE |