| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 04 Jan 2023 | Work Tendered.But No Response.To be Retendered | Perlassery Sn 2 AE | |
| 30 Dec 2022 | Work Tendered.But No Response.To be Retendered | Perlassery Sn 2 AE | |
| 26 Dec 2022 | Work Tendered.But No Response .To be Retendered | Perlassery Sn 2 AE | |
| 21 Dec 2022 | Work Tendered.But No Response .To be Retendered | Perlassery Sn 2 AE | |
| 13 Dec 2022 | Work Tendered.But No Response .To be Retendered | Kannur PH Dn EE | |
| 11 Nov 2022 | TS ISSUED | Kannur PH Dn EE | |
| 19 Sep 2022 | Estimate submitted for OD approval CE,s Office | Perlassery Sn 2 AE | |
| 11 Sep 2022 | Estimate submitted for OD approval CE,s Office | Perlassery Sn 2 AE | |
| 09 Sep 2022 | Estimate submitted for OD approval CE,s Office | Perlassery Sn 2 AE | |
| 03 Sep 2022 | Estimate submitted for OD approval CE,s Office | Perlassery Sn 2 AE |