| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 25 May 2022 | Work in progress. 72% completed. | Kollam WS Sn 2 - AE | |
| 22 May 2022 | Work in progress. 68% completed. | Kollam WS Sn 2 - AE | |
| 17 May 2022 | Work in progress. 28% completed. | Kollam WS Sn 2 - AE | |
| 13 May 2022 | Work in progress. 12% completed | Kollam WS Sn 2 - AE | |
| 10 May 2022 | Work in progress. 8% completed. | Kollam WS Sn 2 - AE | |
| 05 May 2022 | Work started. 2% completed | Kollam WS Sn 2 - AE | |
| 27 Apr 2022 | Demand notice for obtaining road cutting sanction submitted to Division office. | Kollam WS Sn 2 - AE | |
| 22 Apr 2022 | Demand notice for obtaining road cutting sanction submitted to Division office. | Kollam WS Sn 2 - AE | |
| 18 Apr 2022 | Demand notice for obtaining road cutting sanction submitted to Division office. | Kollam WS Sn 2 - AE |