| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 11 Jul 2022 | Bill submitted | Kollam WS Sn 2 - AE | |
| 30 Jun 2022 | Work completed. | Kollam WS Sn 2 - AE | |
| 28 Jun 2022 | 98% completed. | Kollam WS Sn 2 - AE | |
| 25 Jun 2022 | Work in progress. 98% completed. | Kollam WS Sn 2 - AE | |
| 20 Jun 2022 | Work in progress. 96% completed. | Kollam WS Sn 2 - AE | |
| 17 Jun 2022 | Work in progress. 95% completed. | Kollam WS Sn 2 - AE | |
| 13 Jun 2022 | Work in progress. 90% completed | Kollam WS Sn 2 - AE | |
| 01 Jun 2022 | Work in progress. 82% completed | Kollam WS Sn 2 - AE | |
| 30 May 2022 | Work in progress. 78% completed. | Kollam PH Dn EE | |
| 27 May 2022 | Work in progress. 76% completed. | Kollam WS Sn 2 - AE |