| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 30 Dec 2024 | Finishing of plastering works in the remaining portions of check dam | Devikulam AE | |
| 24 Dec 2024 | Supply of Pipes at the work site | Devikulam AE | |
| 11 Dec 2024 | PCC work in check dam completed | Devikulam AE | |
| 22 Nov 2024 | Transportation of materials from down hill to the check dam | Devikulam AE | |
| 20 Nov 2024 | plastering work under progress | Devikulam AE | |
| 16 Nov 2024 | Plastering work for check dam progress | Devikulam AE | |
| 13 Nov 2024 | Pipe testing completed ,Site clearing started | Devikulam AE | |