| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 23 May 2025 | No work done | Devikulam AE | |
| 22 May 2025 | Pressure filter installation work completed | Devikulam AE | |
| 21 May 2025 | pressure filter installation in progress. | Devikulam AE | |
| 20 May 2025 | No work done | Devikulam AE | |
| 19 May 2025 | No work done | Devikulam AE | |
| 17 May 2025 | No work done | Devikulam AE | |
| 16 May 2025 | 42 tap connections completed | Devikulam AE | |
| 16 May 2025 | Tap connection and pcc works under progress | Devikulam AE | |
| 15 May 2025 | Tap connection and pcc works under progress | Devikulam AE | |
| 14 May 2025 | Retaining wall and tap connections under progress | Devikulam AE |