Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
25 Jul 2023 | for manjapra road restoration work in progress.for thuravoor pipe laying work ongoing | Perumbavoor Project Dn AE1 | |
20 Jul 2023 | for manjapra road restoration work in progress.out of 2485 connections 120 HTCs are given till date.for thuravur pipe laying work in progress. | Perumbavoor Project Dn AE1 | |
14 Jul 2023 | for manjapra road restoration work in progress.for thuravoor pipe laying work started. | Perumbavoor Project Dn AE1 | |
04 Jul 2023 | for manjapra work in progress.out of 2485 connections 120 HTCs are given .for thuravoor pipe supplying in progress | Perumbavoor Project Dn AE1 | |
21 Jun 2023 | for manjapra work in progress.for thuravoor pipe supplying work started. | Perumbavoor Project Dn AE1 | |
01 Jun 2023 | For Manjapra Pancahayth pipe laying work and connection work on progress and for Thuravoor Panchayath work order executed | Perumbavoor Project Dn AE1 | |
30 May 2023 | For Manjapra Pancahayth pipe laying work and connection work on progress and for Thuravoor Panchayath tender works under progress. | Perumbavoor Project Dn AE1 | |
26 May 2023 | For Manjapra Pancahayth pipe laying work and connection work on progress and for Thuravoor Panchayath tender works under progress. | Perumbavoor Project Dn AE1 | |
19 May 2023 | For Manjapra Pancahayth pipe laying work and connection work on progress and for Thuravoor Panchayath tender works under progress. | Perumbavoor Project Dn AE1 | |
17 May 2023 | For Manjapra Pancahayth pipe laying work and connection work on progress and for Thuravoor Panchayath tender works under progress. | Perumbavoor Project Dn AE1 |