Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
28 Aug 2023 | for manjapra road restoration work in progress.for thuravoor pipe laying work ongoing | Perumbavoor Project Dn AE1 | |
24 Aug 2023 | for manjapra road restoration work in progress.for thuravoor pipe laying work ongoing | Perumbavoor Project Dn AE1 | |
21 Aug 2023 | for manjapra road restoration work in progress.for thuravoor pipe laying work ongoing | Perumbavoor Project Dn AE1 | |
18 Aug 2023 | for manjapra road restoration work in progress.for thuravoor pipe laying work ongoing | Perumbavoor Project Dn AE1 | |
14 Aug 2023 | for manjapra road restoration work in progress.for thuravoor pipe laying work ongoing | Perumbavoor Project Dn AE1 | |
10 Aug 2023 | for manjapra road restoration work in progress.for thuravoor pipe laying work ongoing | Perumbavoor Project Dn AE1 | |
07 Aug 2023 | for manjapra road restoration work in progress.for thuravoor pipe laying work ongoing | Perumbavoor Project Dn AE1 | |
03 Aug 2023 | for manjapra road restoration work in progress.for thuravoor pipe laying work ongoing | Perumbavoor Project Dn AE1 | |
31 Jul 2023 | for manjapra road restoration work in progress.for thuravoor pipe laying work ongoing | Perumbavoor Project Dn AE1 | |
28 Jul 2023 | for manjapra road restoration work in progress.for thuravoor pipe laying work ongoing | Perumbavoor Project Dn AE1 |