Status Date |
Overall Project Status |
Project Officer |
Contact |
15 Apr 2024 |
for manjapra pipe laying and road restoration work in progress.for thuravoor pipe laying work ongoing, road restoration work ongoing, connection work ongoing. |
Perumbavoor Project Dn AE1 |
|
11 Apr 2024 |
for manjapra pipe laying and road restoration work in progress.for thuravoor pipe laying work ongoing, road restoration work ongoing, connection work ongoing. |
Perumbavoor Project Dn AE1 |
|
04 Apr 2024 |
for manjapra pipe laying and road restoration work in progress.for thuravoor pipe laying work ongoing, road restoration work ongoing, connection work ongoing. |
Perumbavoor Project Dn AE1 |
|
31 Mar 2024 |
for manjapra pipe laying and road restoration work in progress.for thuravoor pipe laying work ongoing, road restoration work ongoing, connection work ongoing. |
Perumbavoor Project Dn AE1 |
|
30 Mar 2024 |
for manjapra pipe laying and road restoration work in progress.for thuravoor pipe laying work ongoing, road restoration work ongoing, connection work ongoing. |
Perumbavoor Project Dn AE1 |
|
28 Mar 2024 |
for manjapra pipe laying and road restoration work in progress.for thuravoor pipe laying work ongoing, road restoration work ongoing, connection work ongoing. |
Perumbavoor Project Dn AE1 |
|
27 Mar 2024 |
for manjapra pipe laying and road restoration work in progress.for thuravoor pipe laying work ongoing, road restoration work ongoing, connection work ongoing. |
Perumbavoor Project Dn AE1 |
|
26 Mar 2024 |
for manjapra pipe laying and road restoration work in progress.for thuravoor pipe laying work ongoing, road restoration work ongoing, connection work ongoing. |
Perumbavoor Project Dn AE1 |
|
25 Mar 2024 |
for manjapra pipe laying and road restoration work in progress.for thuravoor pipe laying work ongoing, road restoration work ongoing, connection work ongoing. |
Perumbavoor Project Dn AE1 |
|
24 Mar 2024 |
for manjapra pipe laying and road restoration work in progress.for thuravoor pipe laying work ongoing, road restoration work ongoing, connection work ongoing. |
Perumbavoor Project Dn AE1 |
|