Status Date |
Overall Project Status |
Project Officer |
Contact |
05 Jan 2024 |
for manjapra pipe laying and road restoration work in progress.for thuravoor pipe laying work ongoing, road restoration work ongoing, connection work ongoing. |
Perumbavoor Project Dn AE1 |
|
03 Jan 2024 |
for manjapra pipe laying and road restoration work in progress.for thuravoor pipe laying work ongoing, road restoration work ongoing, connection work ongoing. |
Perumbavoor Project Dn AE1 |
|
02 Jan 2024 |
for manjapra pipe laying and road restoration work in progress.for thuravoor pipe laying work ongoing, road restoration work ongoing, connection work ongoing. |
Perumbavoor Project Dn AE1 |
|
01 Jan 2024 |
for manjapra pipe laying and road restoration work in progress.for thuravoor pipe laying work ongoing, road restoration work ongoing, connection work ongoing. |
Perumbavoor Project Dn AE1 |
|
29 Dec 2023 |
for manjapra pipe laying and road restoration work in progress.for thuravoor pipe laying work ongoing, road restoration work ongoing, connection work ongoing. |
Perumbavoor Project Dn AE1 |
|
26 Dec 2023 |
for manjapra pipe laying and road restoration work in progress.for thuravoor pipe laying work ongoing, road restoration work ongoing, connection work ongoing. |
Perumbavoor Project Dn AE1 |
|
22 Dec 2023 |
for manjapra pipe laying and road restoration work in progress.for thuravoor pipe laying work ongoing, road restoration work ongoing, connection work ongoing. |
Perumbavoor Project Dn AE1 |
|
19 Dec 2023 |
for manjapra pipe laying and road restoration work in progress.for thuravoor pipe laying work ongoing, road restoration work ongoing, connection work ongoing. |
Perumbavoor Project Dn AE1 |
|
15 Dec 2023 |
for manjapra pipe laying and road restoration work in progress.for thuravoor pipe laying work ongoing, road restoration work ongoing, connection work ongoing. |
Perumbavoor Project Dn AE1 |
|
11 Dec 2023 |
for manjapra pipe laying and road restoration work in progress.for thuravoor pipe laying work ongoing, road restoration work ongoing, connection work ongoing. |
Perumbavoor Project Dn AE1 |
|