| 24 Nov 2022 | Agreement Executed | Devikulam AE | |
| 16 Nov 2022 | One Contractor quoted the work. Work order issued. But Agreement not executed yet | Devikulam AE | |
| 01 Oct 2022 | One Contractor quoted the work. Agreement not executed yet | Devikulam AE | |
| 13 Sep 2022 | One Contractor quoted the work. Agreement not executed yet | Devikulam AE | |
| 24 Aug 2022 | two bids received ,work order to issued | Thodupuzha PH Dn EE | |
| 05 Aug 2022 | Work Tendered | Thodupuzha PH Dn EE | |
| 26 Jul 2022 | The estimate is under scrutiny at Divisional Office | Devikulam AE | |
| 20 Jul 2022 | The estimate is under scrutiny at Divisional Office | Devikulam AE | |
| 13 Jul 2022 | The estimate is under scrutiny at Divisional Office | Devikulam AE | |
| 09 Jul 2022 | The estimate is under scrutiny | Thodupuzha PH Dn EE |