Overall Project Status

Status Date Overall Project Status Project Officer Contact
16 May 2023 pump erection work started. Devikulam AE
11 May 2023 Pump supplied. Pump Erection to be completed Devikulam AE
09 May 2023 Pump supplied ,erection balance Devikulam AE
05 May 2023 Pump supplied ,erection balance Devikulam AE
27 Apr 2023 Pump supplied ,erection will be done on next Tuesday Devikulam AE
19 Apr 2023 Hand rail work started and contractor informed that pump has been delivered from company and it will be erected soon. Devikulam AE
12 Apr 2023 Hand rail work started and contractor informed that pump has been delivered from company and it will be erected next week. Devikulam AE
09 Apr 2023 Hand rail work started and contractor informed that order placed for pump and it will be erected soon Devikulam AE
30 Mar 2023 Hand rail work started and contractor informed that order placed for pump and it will be erected soon Devikulam AE
23 Mar 2023 Hand rail work started and contractor informed that order placed for pump and it will be erected soon Devikulam AE