| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 16 May 2023 | pump erection work started. | Devikulam AE | |
| 11 May 2023 | Pump supplied. Pump Erection to be completed | Devikulam AE | |
| 09 May 2023 | Pump supplied ,erection balance | Devikulam AE | |
| 05 May 2023 | Pump supplied ,erection balance | Devikulam AE | |
| 27 Apr 2023 | Pump supplied ,erection will be done on next Tuesday | Devikulam AE | |
| 19 Apr 2023 | Hand rail work started and contractor informed that pump has been delivered from company and it will be erected soon. | Devikulam AE | |
| 12 Apr 2023 | Hand rail work started and contractor informed that pump has been delivered from company and it will be erected next week. | Devikulam AE | |
| 09 Apr 2023 | Hand rail work started and contractor informed that order placed for pump and it will be erected soon | Devikulam AE | |
| 30 Mar 2023 | Hand rail work started and contractor informed that order placed for pump and it will be erected soon | Devikulam AE | |
| 23 Mar 2023 | Hand rail work started and contractor informed that order placed for pump and it will be erected soon | Devikulam AE |