| 25 Nov 2023 | Disconnection of unusable street tap work in progress. 380 nos Completed | Kottiyam PH Sn AE | |
| 20 Nov 2023 | Disconnection of unusable street tap work in progress. 321 nos Completed | Kottiyam PH Sn AE | |
| 15 Nov 2023 | Disconnection of unusable street tap work in progress. 321 nos Completed | Kottiyam PH Sn AE | |
| 09 Nov 2023 | Disconnection of unusable street tap work in progress. 298 nos Completed | Kottiyam PH Sn AE | |
| 04 Nov 2023 | Disconnection of unusable street tap work in progress. 274 nos Completed | Kottiyam PH Sn AE | |
| 31 Oct 2023 | Disconnection of unusable street tap work in progress. 242 nos Completed | Kottiyam PH Sn AE | |
| 28 Oct 2023 | Disconnection of unusable street tap work in progress. 196 nos Completed | Kottiyam PH Sn AE | |
| 25 Oct 2023 | Disconnection of unusable street tap work in progress. 159 nos Completed | Kottiyam PH Sn AE | |
| 18 Oct 2023 | Disconnection of unusable street tap work in progress. 114 nos Completed | Kottiyam PH Sn AE |