Overall Project Status

Status Date Overall Project Status Project Officer Contact
12 Feb 2024 Disconnection of unusable street tap work in progress. 550 nos Completed Kottiyam PH Sn AE
08 Feb 2024 Disconnection of unusable street tap work in progress. 530 nos Completed. Revised estimate Submitted for approval Kottiyam PH Sn AE
05 Feb 2024 Disconnection of unusable street tap work in progress. 530 nos Completed. Revised estimate Submitted for approval Kottiyam PH Sn AE
01 Feb 2024 Disconnection of unusable street tap work in progress. 530 nos Completed. Revised estimate Submitted for approval Kottiyam PH Sn AE
29 Jan 2024 Disconnection of unusable street tap work in progress. 530 nos Completed. Revised estimate Submitted for approval Kottiyam PH Sn AE
23 Jan 2024 Disconnection of unusable street tap work in progress. 530 nos Completed. Revised estimate Submitted for approval Kottiyam PH Sn AE
19 Jan 2024 Disconnection of unusable street tap work in progress. 530 nos Completed. Revised estimate Submitted for approval Kottiyam PH Sn AE
15 Jan 2024 Disconnection of unusable street tap work in progress. 530 nos Completed. Revised estimate Submitted for approval Kottiyam PH Sn AE
12 Jan 2024 Disconnection of unusable street tap work in progress. 530 nos Completed. Revised estimate Submitted for approval Kottiyam PH Sn AE
09 Jan 2024 Disconnection of unusable street tap work in progress. 530 nos Completed. Revised estimate Submitted for approval Kottiyam PH Sn AE