Status Date Overall Project Status Project Officer Contact
15 Feb 2023 Road restoration work in progress. Out of 11 km - 10.20 km laying work completed. Sasthamcotta WS Sn 1 - AE
24 Jan 2023 Pipe line extension work and road restoration work in progress. Out of 11 km - 10.20 km laying work completed. Sasthamcotta WS Sn 1 - AE
21 Jan 2023 Pipe line extension work and road restoration work in progress. Out of 11 km - 10.20 km laying work completed. Sasthamcotta WS Sn 1 - AE
16 Jan 2023 Pipe line extension work and road restoration work in progress. Out of 11 km - 10.20 km laying work completed. Sasthamcotta WS Sn 1 - AE
09 Jan 2023 Pipe line extension work and road restoration work in progress. Out of 11 km - 10.20 km laying work completed. Sasthamcotta WS Sn 1 - AE
03 Jan 2023 Pipe line extension work and road restoration work in progress. Out of 11 km - 10.20 km laying work completed. Sasthamcotta WS Sn 1 - AE
29 Dec 2022 Pipe line extension work and road restoration work in progress. Out of 11 km - 10.20 km laying work completed. Sasthamcotta WS Sn 1 - AE
21 Dec 2022 Pipe line extension work and road restoration work in progress. Out of 11 km - 10.20 km laying work completed. Sasthamcotta WS Sn 1 - AE
14 Dec 2022 Pipe line extension work and road restoration work in progress. Out of 11 km - 10.20 km laying work completed. Sasthamcotta WS Sn 1 - AE
06 Dec 2022 Pipe line extension work and road restoration work in progress. Out of 11 km - 10.10 km laying work completed. Sasthamcotta WS Sn 1 - AE