Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
15 Feb 2023 | Road restoration work in progress. Out of 11 km - 10.20 km laying work completed. | Sasthamcotta WS Sn 1 - AE | |
24 Jan 2023 | Pipe line extension work and road restoration work in progress. Out of 11 km - 10.20 km laying work completed. | Sasthamcotta WS Sn 1 - AE | |
21 Jan 2023 | Pipe line extension work and road restoration work in progress. Out of 11 km - 10.20 km laying work completed. | Sasthamcotta WS Sn 1 - AE | |
16 Jan 2023 | Pipe line extension work and road restoration work in progress. Out of 11 km - 10.20 km laying work completed. | Sasthamcotta WS Sn 1 - AE | |
09 Jan 2023 | Pipe line extension work and road restoration work in progress. Out of 11 km - 10.20 km laying work completed. | Sasthamcotta WS Sn 1 - AE | |
03 Jan 2023 | Pipe line extension work and road restoration work in progress. Out of 11 km - 10.20 km laying work completed. | Sasthamcotta WS Sn 1 - AE | |
29 Dec 2022 | Pipe line extension work and road restoration work in progress. Out of 11 km - 10.20 km laying work completed. | Sasthamcotta WS Sn 1 - AE | |
21 Dec 2022 | Pipe line extension work and road restoration work in progress. Out of 11 km - 10.20 km laying work completed. | Sasthamcotta WS Sn 1 - AE | |
14 Dec 2022 | Pipe line extension work and road restoration work in progress. Out of 11 km - 10.20 km laying work completed. | Sasthamcotta WS Sn 1 - AE | |
06 Dec 2022 | Pipe line extension work and road restoration work in progress. Out of 11 km - 10.10 km laying work completed. | Sasthamcotta WS Sn 1 - AE |