Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
29 Mar 2023 | Road restoration work in progress. Out of 11 km - 10.20 km laying work completed. | Sasthamcotta WS Sn 1 - AE | |
24 Mar 2023 | Road restoration work in progress. Out of 11 km - 10.20 km laying work completed. | Sasthamcotta WS Sn 1 - AE | |
27 Feb 2023 | Road restoration work in progress. Out of 11 km - 10.20 km laying work completed. | Sasthamcotta WS Sn 1 - AE | |
22 Feb 2023 | Road restoration work in progress. Out of 11 km - 10.20 km laying work completed. | Sasthamcotta WS Sn 1 - AE | |
15 Feb 2023 | Road restoration work in progress. Out of 11 km - 10.20 km laying work completed. | Sasthamcotta WS Sn 1 - AE | |
09 Feb 2023 | Pipe line extension work and road restoration work in progress. Out of 11 km - 10.20 km laying work completed. | Sasthamcotta WS Sn 1 - AE | |
03 Feb 2023 | Road restoration work in progress. Out of 11 km - 10.20 km laying work completed. | Sasthamcotta WS Sn 1 - AE | |
24 Jan 2023 | Pipe line extension work and road restoration work in progress. Out of 11 km - 10.20 km laying work completed. | Sasthamcotta WS Sn 1 - AE | |
27 Feb 2023 | Road restoration work in progress. Out of 11 km - 10.20 km laying work was completed. | Sasthamcotta WS Sn 1 - AE | |
22 Feb 2023 | Road restoration work in progress. Out of 11 km - 10.20 km laying work was completed. | Sasthamcotta WS Sn 1 - AE |