29 Mar 2023 Road restoration work in progress. Out of 11 km - 10.20 km laying work completed. Sasthamcotta WS Sn 1 - AE
24 Mar 2023 Road restoration work in progress. Out of 11 km - 10.20 km laying work completed. Sasthamcotta WS Sn 1 - AE
27 Feb 2023 Road restoration work in progress. Out of 11 km - 10.20 km laying work completed. Sasthamcotta WS Sn 1 - AE
22 Feb 2023 Road restoration work in progress. Out of 11 km - 10.20 km laying work completed. Sasthamcotta WS Sn 1 - AE
15 Feb 2023 Road restoration work in progress. Out of 11 km - 10.20 km laying work completed. Sasthamcotta WS Sn 1 - AE
09 Feb 2023 Pipe line extension work and road restoration work in progress. Out of 11 km - 10.20 km laying work completed. Sasthamcotta WS Sn 1 - AE
03 Feb 2023 Road restoration work in progress. Out of 11 km - 10.20 km laying work completed. Sasthamcotta WS Sn 1 - AE
24 Jan 2023 Pipe line extension work and road restoration work in progress. Out of 11 km - 10.20 km laying work completed. Sasthamcotta WS Sn 1 - AE
27 Feb 2023 Road restoration work in progress. Out of 11 km - 10.20 km laying work was completed. Sasthamcotta WS Sn 1 - AE
22 Feb 2023 Road restoration work in progress. Out of 11 km - 10.20 km laying work was completed. Sasthamcotta WS Sn 1 - AE