Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

JJM-Ayavana-Providing FHTC to households of Ayavana Panchayath in Ernakulam District

Project JJM-Ayavana-Providing FHTC to households of Ayavana Panchayath in Ernakulam District
Project Code EKMJJM092110905
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description The components of project proposal consist of i. 6.0 m diameter intake well cum pump house(Existing), ii. 1600 m of 200mm DI K9 raw water pumping main (existing), iii. 2 numbers 50HP VT raw water pump sets, (one stand bye) iv. 2.50 mld SSF Treatment Plant, 4.50 LL clear water sump(Existing), v. 2.10mld Pressure filter Treatment Plant at Intake well site, vi. 100 m of 150mm DI K9 for Zone 1-HighLevel (Existing), vii. 4200 m of 100 mm DI K9 for Zone 2 viii. 6100 m of 200 mm DI K9 clear water pumping mains for Zone3. ix. Clear water Pumps 40 HP VT, 5 HP, & 10 HP Centrifugal pump set x. OHSR of capacity 4.50 lakh liters at Kalampoor for Zone 3, xi. existing OHSR of capacity 3.0 lakh litres at WTP for Zone 1-High Level. xii.GLSR of capacity 0.60 lakh litres near Valiyapara for Zone 2. xiii. Sump of capacity 4.50 lakh litres at WTP for Zone1-Low Level. xiv. Distribution systems in Zone I, II & III. xv. 2728nos new water connections (FHTC) in all zones of Ayavana Panchayath and Shifting 2428nos existing service connections to the newly laid line.
Status On-going
District Ernakulam
Executing Office Perumbavoor Project Dn
AS Amount (Rs) 299600000
AS Number G.O.(Rt)No.489/2021/WRD
TS Amount (Rs) 297600000
TS Number TS/2021-2022/2021/13108 Dated: 09-12-2021
Total Bill Submitted (Rs) 127267490
Total Bill Paid (Rs) 127267490
Population Benefitted 20539
Capacity in MLD 3.07
Actual Project Completion Date 04 May 2022
Coverage Ayavana Panchyath in Ernakulam district
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 JJM-Ayavana-Providing FHTC to households of Ayavana Panchayath in Ernakulam District Project Division Piravom(Kattapana)

Overall Project Status

Status Date Overall Project Status Project Officer Contact
02 Nov 2023 91% of overall work is completed ,renovation of Well-cum-Pumphouse , Replacing of filter media , constuction of OHSR at Kalampoor Para & GLSR at Valyapara etc. completed .130km pipelines laid. Erection of pumpsets , erection of pressure filter gap closing of pumping and distribution mains are in progress.FHTC work on going. Piravam Project Sub Dn AE 2
07 Sep 2023 90% of overall work is completed ,renovation of Well-cum-Pumphouse , Replacing of filter media , constuction of OHSR at Kalampoor Para & GLSR at Valyapara etc. completed .130km pipelines laid. Erection of pumpsets , erection of pressure filter gap closing of pumping and distribution mains are in progress. Piravam Project Sub Dn AE 2
24 Aug 2023 Ayavana JJM updates: Well cleaning completed and renovation in progress,Pumpsets techinal data submitted for approval,Pressure filter erection in progress,SSF renovated-filter media changed(completed),OHSR structure completed-plastering in progress,GLSR -completed-plastering in progress,Laying of distribution lines and pumping mains-80% completed,FHTC's-1037 given.Pump supplied. Piravam Project Sub Dn AE 2
24 Aug 2023 90% of overall work is completed,renovation of Well-cum-Pumphouse Replacing of filter media , constuction of OHSR at Kalampoor Para & GLSR at Valyapara etc. completed .130km pipelines laid. Erection of pumpsets , erection of pressure filter gap closing of pumping and distribution mains are in progress. Piravam Project Sub Dn AE 2
17 Aug 2023 Ayavana JJM updates: Well cleaning completed and renovation in progress,Pumpsets techinal data submitted for approval,Pressure filter erection in progress,SSF renovated-filter media changed(completed),OHSR structure completed-plastering in progress,GLSR -completed-plastering in progress,Laying of distribution lines and pumping mains-80% completed,FHTC's-736 given.Pump supplied. Piravam Project Sub Dn AE 2

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 18/04/2022
Scheduled date of Completion of the Project 17 Jan 2023
Expected date of Completion 30/06/2023

Processing Dates

AS Date 18 Sep 2021
TS Date 09 Dec 2021

Other details

Project Officers View