JJM-Ayavana-Providing FHTC to households of Ayavana Panchayath in Ernakulam District
Project |
JJM-Ayavana-Providing FHTC to households of Ayavana Panchayath in Ernakulam District |
Project Code |
EKMJJM092110905 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
The components of project proposal consist of
i. 6.0 m diameter intake well cum pump house(Existing),
ii. 1600 m of 200mm DI K9 raw water pumping main (existing),
iii. 2 numbers 50HP VT raw water pump sets, (one stand bye)
iv. 2.50 mld SSF Treatment Plant, 4.50 LL clear water sump(Existing),
v. 2.10mld Pressure filter Treatment Plant at Intake well site,
vi. 100 m of 150mm DI K9 for Zone 1-HighLevel (Existing),
vii. 4200 m of 100 mm DI K9 for Zone 2
viii. 6100 m of 200 mm DI K9 clear water pumping mains for Zone3.
ix. Clear water Pumps 40 HP VT, 5 HP, & 10 HP Centrifugal pump set
x. OHSR of capacity 4.50 lakh liters at Kalampoor for Zone 3,
xi. existing OHSR of capacity 3.0 lakh litres at WTP for Zone 1-High Level.
xii.GLSR of capacity 0.60 lakh litres near Valiyapara for Zone 2.
xiii. Sump of capacity 4.50 lakh litres at WTP for Zone1-Low Level.
xiv. Distribution systems in Zone I, II & III.
xv. 2728nos new water connections (FHTC) in all zones of Ayavana
Panchayath and Shifting 2428nos existing service connections to the
newly laid line. |
Status |
On-going |
District |
Ernakulam |
Executing Office |
Perumbavoor Project Dn |
AS Amount (Rs) |
299600000
|
AS Number |
G.O.(Rt)No.489/2021/WRD |
TS Amount (Rs) |
297600000 |
TS Number |
TS/2021-2022/2021/13108 Dated: 09-12-2021 |
Total Bill Submitted (Rs) |
127267490 |
Total Bill Paid (Rs) |
127267490 |
Population Benefitted |
20539 |
Capacity in MLD |
3.07 |
Actual Project Completion Date |
04 May 2022 |
Coverage |
Ayavana Panchyath in Ernakulam district |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
JJM-Ayavana-Providing FHTC to households of Ayavana Panchayath in Ernakulam District |
Project Division Piravom(Kattapana) |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
02 Nov 2023 |
91% of overall work is completed ,renovation of Well-cum-Pumphouse , Replacing of filter media , constuction of OHSR at Kalampoor Para & GLSR at Valyapara etc. completed .130km pipelines laid. Erection of pumpsets , erection of pressure filter gap closing of pumping and distribution mains are in progress.FHTC work on going. |
Piravam Project Sub Dn AE 2 |
|
07 Sep 2023 |
90% of overall work is completed ,renovation of Well-cum-Pumphouse , Replacing of filter media , constuction of OHSR at Kalampoor Para & GLSR at Valyapara etc. completed .130km pipelines laid. Erection of pumpsets , erection of pressure filter gap closing of pumping and distribution mains are in progress. |
Piravam Project Sub Dn AE 2 |
|
24 Aug 2023 |
Ayavana JJM updates: Well cleaning completed and renovation in progress,Pumpsets techinal data submitted for approval,Pressure filter erection in progress,SSF renovated-filter media changed(completed),OHSR structure completed-plastering in progress,GLSR -completed-plastering in progress,Laying of distribution lines and pumping mains-80% completed,FHTC's-1037 given.Pump supplied. |
Piravam Project Sub Dn AE 2 |
|
24 Aug 2023 |
90% of overall work is completed,renovation of Well-cum-Pumphouse Replacing of filter media , constuction of OHSR at Kalampoor Para & GLSR at Valyapara etc. completed .130km pipelines laid. Erection of pumpsets , erection of pressure filter gap closing of pumping and distribution mains are in progress. |
Piravam Project Sub Dn AE 2 |
|
17 Aug 2023 |
Ayavana JJM updates: Well cleaning completed and renovation in progress,Pumpsets techinal data submitted for approval,Pressure filter erection in progress,SSF renovated-filter media changed(completed),OHSR structure completed-plastering in progress,GLSR -completed-plastering in progress,Laying of distribution lines and pumping mains-80% completed,FHTC's-736 given.Pump supplied. |
Piravam Project Sub Dn AE 2 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
18/04/2022 |
Scheduled date of Completion of the Project |
17 Jan 2023 |
Expected date of Completion |
30/06/2023 |
Processing Dates
AS Date |
18 Sep 2021 |
TS Date |
09 Dec 2021 |