Status Date |
Overall Project Status |
Project Officer |
Contact |
02 Nov 2023 |
91% of overall work is completed ,renovation of Well-cum-Pumphouse , Replacing of filter media , constuction of OHSR at Kalampoor Para & GLSR at Valyapara etc. completed .130km pipelines laid. Erection of pumpsets , erection of pressure filter gap closing of pumping and distribution mains are in progress.FHTC work on going. |
Piravam Project Sub Dn AE 2 |
|
07 Sep 2023 |
90% of overall work is completed ,renovation of Well-cum-Pumphouse , Replacing of filter media , constuction of OHSR at Kalampoor Para & GLSR at Valyapara etc. completed .130km pipelines laid. Erection of pumpsets , erection of pressure filter gap closing of pumping and distribution mains are in progress. |
Piravam Project Sub Dn AE 2 |
|
24 Aug 2023 |
Ayavana JJM updates: Well cleaning completed and renovation in progress,Pumpsets techinal data submitted for approval,Pressure filter erection in progress,SSF renovated-filter media changed(completed),OHSR structure completed-plastering in progress,GLSR -completed-plastering in progress,Laying of distribution lines and pumping mains-80% completed,FHTC's-1037 given.Pump supplied. |
Piravam Project Sub Dn AE 2 |
|
24 Aug 2023 |
90% of overall work is completed,renovation of Well-cum-Pumphouse Replacing of filter media , constuction of OHSR at Kalampoor Para & GLSR at Valyapara etc. completed .130km pipelines laid. Erection of pumpsets , erection of pressure filter gap closing of pumping and distribution mains are in progress. |
Piravam Project Sub Dn AE 2 |
|
17 Aug 2023 |
Ayavana JJM updates: Well cleaning completed and renovation in progress,Pumpsets techinal data submitted for approval,Pressure filter erection in progress,SSF renovated-filter media changed(completed),OHSR structure completed-plastering in progress,GLSR -completed-plastering in progress,Laying of distribution lines and pumping mains-80% completed,FHTC's-736 given.Pump supplied. |
Piravam Project Sub Dn AE 2 |
|
11 Aug 2023 |
Ayavana JJM updates: Well cleaning completed and renovation in progress,Pumpsets techinal data submitted for approval,Pressure filter erection in progress,SSF renovated-filter media changed(completed),OHSR structure completed-plastering in progress,GLSR -completed-plastering in progress,Laying of distribution lines and pumping mains-80% completed,FHTC's-636 given. |
Piravam Project Sub Dn AE 2 |
|
04 Aug 2023 |
Ayavana JJM updates: Well cleaning completed and renovation in progress,Pumpsets techinal data submitted for approval,Pressure filter erection in progress,SSF renovated-filter media changed(completed),OHSR structure completed-plastering in progress,GLSR -completed-plastering in progress,Laying of distribution lines and pumping mains-80% completed,FHTC's-636 given. |
Piravam Project Sub Dn AE 2 |
|
29 Jul 2023 |
Ayavana JJM updates: Well cleaning completed and renovation in progress,Pumpsets techinal data submitted for approval,Pressure filter erection in progress,SSF renovated-filter media changed(completed),OHSR structure completed-plastering in progress,GLSR -completed-plastering in progress,Laying of distribution lines and pumping mains-82% completed,FHTC's-636 given |
Piravam Project Sub Dn AE 2 |
|
19 Jul 2023 |
Ayavana JJM updates: Well cleaning completed and renovation in progress,Pumpsets techinal data submitted for approval,Pressure filter erection in progress,SSF renovated-filter media changed(completed),OHSR structure completed-plastering in progress,GLSR -completed-plastering in progress,Laying of distribution lines and pumping mains-82% completed,FHTC's-636 given |
Piravam Project Sub Dn AE 2 |
|
30 Jun 2023 |
Ayavana JJM updates: Well cleaning completed and renovation in progress,Pumpsets techinal data submitted for approval,Pressure filter erection in progress,SSF renovated-filter media changed(completed),OHSR structure completed-plastering in progress,GLSR -completed-plastering in progress,Laying of distribution lines and pumping mains-80% completed,FHTC's-530 given |
Piravam Project Sub Dn AE 2 |
|