Project | JJM-Ayavana-Providing FHTC to households of Ayavana Panchayath in Ernakulam District |
---|---|
Project Code | EKMJJM092110905P2 |
Type | Package |
Main Project | JJM-Ayavana-Providing FHTC to households of Ayavana Panchayath in Ernakulam District |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | JJM-Ayavana-Providing FHTC to households of Ayavana Panchayath in Ernakulam District |
Status | On-going |
District | Ernakulam |
Executing Office | Piravam Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 297600000 |
TS Number | TS/2021-2022/2021/13108 Dated: 09-12-2021 |
Technical specification | 2 OHSR,1 pressure filter,pumping,distribution mains |
Contractor | FRANCIS N A (Mob: 9447576403) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 18/04/2022 |
---|---|
Scheduled date of Completion as per agreement | 17 Jan 2023 |
Expected date of Completion | 17/07/2023 |
TS Date | 09 Dec 2021 |
---|---|
Estimate Approval | 09 Dec 2021 |
NIT Approval | 09 Dec 2021 |
Tender Closing | 14 Jun 2023 |
Price bid opening | 10 Mar 2023 |
Workorder Date | 18 Apr 2022 |
---|---|
NA | 04 May 2022 |
Piravam Project Sub Dn AE 2 |
Date: 17/05/2024 |
Work in progress | 95% Completed
95% of overall work is completed ,renovation of Well-cum-Pumphouse , Replacing of filter media , constuction of OHSR at Kalampoor Para & GLSR at Valyapara etc. completed .130 km pipelines laid. Erection of pumpsets , erection of pressure filter gap closing of pumping and distribution mains are in progress.Laying of 10 km CWPM completed,145 km distribution pipe laying completed & 1568 nos of fhtcs ,120 nos htcs given.New connections , reconnections & inter connection works are on going at Ayavana panchayath..
Piravam Project Sub Dn AE 2 |
Date: 14/05/2024 |
Work in progress | 95% Completed
95% of overall work is completed ,renovation of Well-cum-Pumphouse , Replacing of filter media , constuction of OHSR at Kalampoor Para & GLSR at Valyapara etc. completed .130 km pipelines laid. Erection of pumpsets , erection of pressure filter gap closing of pumping and distribution mains are in progress.Laying of 10 km CWPM completed,145 km distribution pipe laying completed & 1568 nos of fhtcs ,120 nos htcs given.New connections , reconnections & inter connection works are on going at Ayavana panchayath..