JJM-Ayavana-Providing FHTC to households of Ayavana Panchayath in Ernakulam District

Project JJM-Ayavana-Providing FHTC to households of Ayavana Panchayath in Ernakulam District
Project Code EKMJJM092110905P2
Type Package
Main Project JJM-Ayavana-Providing FHTC to households of Ayavana Panchayath in Ernakulam District
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description JJM-Ayavana-Providing FHTC to households of Ayavana Panchayath in Ernakulam District
Status On-going
District Ernakulam
Executing Office Piravam Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 297600000
TS Number TS/2021-2022/2021/13108 Dated: 09-12-2021
Technical specification 2 OHSR,1 pressure filter,pumping,distribution mains
Contractor FRANCIS N A (Mob: 9447576403)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 18/04/2022
Scheduled date of Completion as per agreement 17 Jan 2023
Expected date of Completion 17/07/2023

Processing Dates

TS Date 09 Dec 2021
Estimate Approval 09 Dec 2021
NIT Approval 09 Dec 2021
Tender Closing 14 Jun 2023
Price bid opening 10 Mar 2023

Approval Dates

Workorder Date 18 Apr 2022
NA 04 May 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Piravam Project Sub Dn AE 2
Date: 17/05/2024

Work in progress | 95% Completed

95% of overall work is completed ,renovation of Well-cum-Pumphouse , Replacing of filter media , constuction of OHSR at Kalampoor Para & GLSR at Valyapara etc. completed .130 km pipelines laid. Erection of pumpsets , erection of pressure filter gap closing of pumping and distribution mains are in progress.Laying of 10 km CWPM completed,145 km distribution pipe laying completed & 1568 nos of fhtcs ,120 nos htcs given.New connections , reconnections & inter connection works are on going at Ayavana panchayath..

Piravam Project Sub Dn AE 2
Date: 14/05/2024

Work in progress | 95% Completed

95% of overall work is completed ,renovation of Well-cum-Pumphouse , Replacing of filter media , constuction of OHSR at Kalampoor Para & GLSR at Valyapara etc. completed .130 km pipelines laid. Erection of pumpsets , erection of pressure filter gap closing of pumping and distribution mains are in progress.Laying of 10 km CWPM completed,145 km distribution pipe laying completed & 1568 nos of fhtcs ,120 nos htcs given.New connections , reconnections & inter connection works are on going at Ayavana panchayath..