AMRUT - Kannur Corporation - Supply and laying New distribution line in Pallikkunnu and Puzhathi Zone, providing house connection and inter connection with existing line

Project AMRUT - Kannur Corporation - Supply and laying New distribution line in Pallikkunnu and Puzhathi Zone, providing house connection and inter connection with existing line
Project Code KNRAMRUT11172770
Type Main project
Funding Agency AMRUT
Category AMRUT
Type of scheme Water Supply
Scheme AMRUT
Description Supplying and laying New distribution line in Pallikkunnu and Puzhathi Zone of Kannur Corporation, providing house connection and inter connection with existing line.Total distribution line-20500m(160mm PVC-20500m)
Status Completed
District Kannur
Executing Office Kannur Project Dn
AS Amount (Rs) 42700000
AS Number
TS Amount (Rs)
TS Number
Total Bill Submitted (Rs) 25175165
Total Bill Paid (Rs) 38875165
Population Benefitted 63032
Capacity in MLD
Actual Project Completion Date Date is not specified
Coverage 63032(population)65715(2050)13208(Habitation)

Packages

No. Project Name Location View
1 AMRUT - WSS to Kannur Corporation - Supply and laying New distribution line in Pallikkunnu and Puzhathi Zone, providing house connection and inter connection with existing line-Package I Kannur Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
05 Jan 2021 100% work comleted Koothuparamba Project Sn No 1
05 Jan 2021 New house connections completed. Koothuparamba Project Sn No 1
13 Sep 2020 Pipe laying completed and charged.Shifting of existing connection to the new line 245nos. out of 250nos. completed. Providing new house connection 210nos. completed. Koothuparamba Project Sn No 1
13 Sep 2020 Pipe laying work 95% work completed. Shifting of old house connections 245Nos. out of 250nos. completed. New house connection work in progress. Koothuparamba Project Sn No 1

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 04/12/2018
Scheduled date of Completion of the Project 19 Dec 2018
Expected date of Completion 31/12/2020

Processing Dates

AS Date 02 Nov 2017
TS Date 27 Nov 2017
Estimate Approval 27 Nov 2017
Tender Closing 11 Jan 2018
Technichal Pre-Qualification 21 Feb 2018
Price bid opening 22 Feb 2018

Approval Dates

CE Approval 12 Mar 2018
Workorder Date 20 Mar 2018
NA 05 Apr 2018