Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
05 Jan 2021 | 100% work comleted | Koothuparamba Project Sn No 1 | |
05 Jan 2021 | New house connections completed. | Koothuparamba Project Sn No 1 | |
13 Sep 2020 | Pipe laying completed and charged.Shifting of existing connection to the new line 245nos. out of 250nos. completed. Providing new house connection 210nos. completed. | Koothuparamba Project Sn No 1 | |