Project | AMRUT - WSS to Kannur Corporation - Supply and laying New distribution line in Pallikkunnu and Puzhathi Zone, providing house connection and inter connection with existing line-Package I |
---|---|
Project Code | KNRAMRUT11172770P1 |
Type | Package |
Main Project | AMRUT - Kannur Corporation - Supply and laying New distribution line in Pallikkunnu and Puzhathi Zone, providing house connection and inter connection with existing line |
Funding Agency | AMRUT |
Category | AMRUT |
Type of scheme | Water Supply |
Scheme | AMRUT |
Description | Supply and laying New distribution line in Pallikkunnu and Puzhathi Zone od Kannur Corporation, providing house connection and inter connection with existing line |
Status | Completed |
District | Kannur |
Executing Office | Kannur Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | |
TS Number | |
Technical specification | Supplying and laying new distribution line to Pallikkunnu and puzhathi zone of Kannur Corporation . Supplying 160mm 6kg/cm2 PVC pipes and specials including constrcution of valve chambers,anchor block, cross walls ,fixing control valves and air valves,fabrication of MS pipes,providing new house connections and interconnections with existing line . |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 04/12/2018 |
---|---|
Scheduled date of Completion as per agreement | Date is not specified |
Expected date of Completion | 31/12/2020 |
AS Date | 02 Nov 2017 |
---|---|
TS Date | 27 Nov 2017 |
Estimate Approval | 27 Nov 2017 |
Workorder Date | 20 Mar 2018 |
---|---|
NA | 04 May 2018 |
Koothuparamba Project Sn No 1 |
Date: 11/02/2021 |
Work has been completed | 100% Completed
Work completed on 31.12.2020.
Koothuparamba Project Sn No 1 |
Date: 31/07/2020 |
Work in progress | 98% Completed
Pipe laying completed and charged.Shifting of existing connection to the new line 245/250 completed. Providing new house connection 210nos. completed..