STATE PLAN 2017-18- IMPROVEMENT OF WSS TO SPECIFIED INSTITUTIONS – MEDICAL COLLEGE, KOTTAYAM Supplying and providing 150 mm2 ABC 3 core cable from Gandhinagar KSEB substation to WTP at Medical College, Kottayam for ensuring uninterrupted power supply to WTP, Medical College, Kottayam - 900 mts 2 Improvements of existing substation by providing stand by transformer facility (400 KVA) with yard expansion work at WTP Compound, Medical College, Kottayam 3 Renovation of WTP including reconditioning of clarifloculator, filter media & necessary improvement works for ensuring water quality by providing quality testing & monitoring facility. 4 Construction of new pump house, realignment of pump sets & connected renovation works 5 Renovation of totally damaged road by re-tarring / concreting work, constructiong compound wall , yard lighting work, fencing work etc.
| Project |
STATE PLAN 2017-18- IMPROVEMENT OF WSS TO SPECIFIED INSTITUTIONS – MEDICAL COLLEGE, KOTTAYAM Supplying and providing 150 mm2 ABC 3 core cable from Gandhinagar KSEB substation to WTP at Medical College, Kottayam for ensuring uninterrupted power supply to WTP, Medical College, Kottayam - 900 mts 2 Improvements of existing substation by providing stand by transformer facility (400 KVA) with yard expansion work at WTP Compound, Medical College, Kottayam 3 Renovation of WTP including reconditioning of clarifloculator, filter media & necessary improvement works for ensuring water quality by providing quality testing & monitoring facility. 4 Construction of new pump house, realignment of pump sets & connected renovation works 5 Renovation of totally damaged road by re-tarring / concreting work, constructiong compound wall , yard lighting work, fencing work etc. |
| Project Code |
KTMGOK12171000 |
| Type |
Main project |
| Funding Agency |
GOK |
| Category |
State plan |
| Type of scheme |
Water Supply |
| Scheme |
4215-01-800-89 |
| Description |
STATE PLAN 2017-18- IMPROVEMENT OF WSS TO SPECIFIED INSTITUTIONS – MEDICAL COLLEGE, KOTTAYAM
Sl No Proposal Amount in Lakhs
1 Supplying and providing 150 mm2 ABC 3 core cable from Gandhinagar KSEB substation to WTP at Medical College, Kottayam for ensuring uninterrupted power supply to WTP, Medical College, Kottayam - 900 mts @ Rs.2500 / M ₹ 22.50
2 Improvements of existing substation by providing stand by transformer facility (400 KVA) with yard expansion work at WTP Compound, Medical College, Kottayam ₹ 35.00
3 Renovation of WTP including reconditioning of clarifloculator, filter media & necessary improvement works for ensuring water quality by providing quality testing & monitoring facility. ₹ 25.00
4 Construction of new pump house, realignment of pump sets & connected renovation works ₹ 10.00
5 Renovation of totally damaged road by re-tarring / concreting work, constructiong compound wall , yard lighting work, fencing work etc. ₹ 40.00
|
| Status |
Completed |
| District |
Kottayam |
| Executing Office |
Kottayam PH Dn |
| AS Amount (Rs) |
13250000
|
| AS Number |
GO(Rt) 419/2019/WRD |
| TS Amount (Rs) |
1465000 |
| TS Number |
TS/2019-2020/2019/13130 |
| Total Bill Submitted (Rs) |
3258689 |
| Total Bill Paid (Rs) |
1350000 |
| Population Benefitted |
1500 |
| Capacity in MLD |
25.00 |
| Actual Project Completion Date |
03 Jun 2021 |
| Coverage |
100% |
| Implementation Schedule |
Download |
| Work Plan |
Download |
Packages
| No. |
Project Name |
Location |
View |
| 1 |
Improvements to substation by providing stand by transformer(400 KVA) including yard expansion work |
Gandhinagar Kottayam PH Med. Col Sn |
|
| 2 |
Re-alignment of pump sets & connected renovation works |
Gandhinagar Kottayam PH Med. Col Sn |
|
| 3 |
Renovation of damaged approach road to WTP Medical college by Re-tarring /Concreting |
Kottayam PH Dn |
|
| 4 |
Renovation of WTP |
Gandhinagar Kottayam PH Med. Col Sn |
|
| 5 |
Supplying and providing 150 mm2 ABC 3 core cable from Gandhinagar KSEB substation to WTP at Medical College, Kottayam |
Kottayam PH Dn |
|
Overall Project Status
| Status Date |
Overall Project Status |
Project Officer |
Contact |
| 20 May 2022 |
Among the 5 Sub Packages 2 Package completed (Road Tarring and KSEB) and balance 3 works no bidder Participation after repeated tenders. As per the VC dated 03-06-21, TM directed to recast the Estimate for Transformer as Stand Bye Transformer is necessary considering Medical College. TS has been cancelled and Estimate under recasting |
Kottayam PHMC AE |
|
| 22 Apr 2022 |
Among the 5 Sub Packages 2 Package completed (Road Tarring and KSEB) and balance 3 works no bidder Participation after repeated tenders. As per the VC dated 03-06-21, TM directed to recast the Estimate for Transformer as Stand Bye Transformer is necessary considering Medical College. TS has been cancelled and Estimate under recasting |
Kottayam PHMC AE |
|
| 20 Apr 2022 |
2022 Among the 5 Sub Packages 2 Package completed (Road Tarring and KSEB) and balance 3 works no bidder Participation after repeated tenders. As per the VC dated 03-06-21, TM directed to recast the Estimate for Transformer as Stand Bye Transformer is necessary considering Medical College. TS has been cancelled and Estimate under recasting |
Kottayam PHMC AE |
|
| 16 Apr 2022 |
Among the 5 Sub Packages 2 Package completed (Road Tarring and KSEB) and balance 3 works no bidder Participation after repeated tenders. As per the VC dated 03-06-21, TM directed to recast the Estimate for Transformer as Stand Bye Transformer is necessary considering Medical College. TS has been cancelled and Estimate under recasting |
Kottayam PHMC AE |
|
| 13 Apr 2022 |
Among the 5 Sub Packages 2 Package completed (Road Tarring and KSEB) and balance 3 works no bidder Participation after repeated tenders. As per the VC dated 03-06-21, TM directed to recast the Estimate for Transformer as Stand Bye Transformer is necessary considering Medical College. TS has been cancelled and Estimate under recasting |
Kottayam PHMC AE |
|
No project review have been added to this project
Duration & Sanction dates
| Date of start of Project |
01/10/2019 |
| Scheduled date of Completion of the Project |
31 Mar 2021 |
| Expected date of Completion |
31/08/2021 |
Processing Dates
| AS Date |
20 Dec 2017 |
| TS Date |
20 Jul 2018 |