Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Re-alignment of pump sets & connected renovation works

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package Date is not specified
Scheduled date of Completion as per agreement Date is not specified
Expected date of Completion Date is not specified

Processing Dates

TS Date 20 Jul 2018
Estimate Approval 28 Sep 2018
Tender Closing 20 May 2021

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kottayam PHMC AE
Date: 03/05/2023

Work has started | 0% Completed

WORK ARRANGED THROUGH JJM ARPOORKKARA.

Kottayam PHMC AE
Date: 20/05/2022

Work has started | 0% Completed

DROPPED.