Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

22 AMRUT ATAL MISSION FOR REJUVENATION AND URBAN TRA(75)-AMRUT-Augmentation of WSS in Kollam Corporation(8518)

Project 22 AMRUT ATAL MISSION FOR REJUVENATION AND URBAN TRA(75)-AMRUT-Augmentation of WSS in Kollam Corporation(8518)
Project Code KLMAMRUT0917464
Type Main project
Funding Agency AMRUT
Category AMRUT
Type of scheme Water Supply
Scheme AMRUT
Description AMRUT-Augmentation of WSS in Kollam Corporation Phase I
Status On-going
District Kollam
Executing Office Kollam Project Dn
AS Amount (Rs) 1044230000
AS Number GO(Rt)No 315/2022/LSGD dated 12/02/2022
TS Amount (Rs) 1044230000
TS Number TS/2017-18/2017/3672 dated 22.12.2017, KWA/CE SR /107/2019-20 dated 04.09.2019, 2017-2018/842 dated 07.03.2018,237/2017-18 /Se/Q dated 21.04.2018,KWA/CE(SR)/PHQ/3292/2016(PARTIV)
Total Bill Submitted (Rs) 364438652
Total Bill Paid (Rs) 287128840
Population Benefitted 429294
Capacity in MLD 100.00
Actual Project Completion Date 30 Jun 2023
Coverage Kollam Corporation and Kottamkara Panchayath
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Construction of 12m dia intake well at Njankadavu SAAP YEAR 2017-18 Kollam Project Dn
2 I) Construction of weir at Njnkadavu across Kallada river SAAP YEAR 2015-16 Kollam Project Dn
3 III)Transformer power line extension SAAP YEAR 2017-18 Kollam Project Dn
4 IV) Design, Construction, Commissioning and maintaining of 100MLD WTP at Vasoorichira SAAP YEAR 2016-17 Kollam Project Dn
5 Supplying laying commissioning and maintaining 500mm DI K9 CWPM from TP to OHSR at Vadakkevila (3520m) SAAP YEAR 2015-16) Kollam Project Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
11 Jan 2024 Packages 1, 4,,5 are completed and the package of 2 – Construction of weir at Njnkadavu across Kallada river – Work Re- Tendered with bid submission date as on 26/06/2023 and tender opening date as on 27-06-2023. Tender opened, two bidders participated. Prequalified by the STC. Price bid opened on 21/7/2023 and Submitted for negotiation to the contractor on 29/7/2023. After negotiation tender submitted to CE's office for sanction on 8/8/2023.Tender submitted to Government for sanction on 2/9/2023. Package 3- 100MLD WTP at Vasoorichira - Components 1.Cascade Aerator 2.Raw water channel 3.Flash mixer 4.Clarrifloculators 5.Filter House 6.Chemical House 7.Admin Building 8.Chlorine Building 9. Wash water Recovery tank 10.Sludge sump 11. Bypass channel 12.Connecting channels All component-related works were completed except external works including stormwater drain which was not done due to public protest. Kollam Project HD
10 Jan 2024 Packages 1, 4,,5 are completed and the package of 2 – Construction of weir at Njnkadavu across Kallada river – Work Re- Tendered with bid submission date as on 26/06/2023 and tender opening date as on 27-06-2023. Tender opened, two bidders participated. Prequalified by the STC. Price bid opened on 21/7/2023 and Submitted for negotiation to the contractor on 29/7/2023. After negotiation tender submitted to CE's office for sanction on 8/8/2023.Tender submitted to Government for sanction on 2/9/2023. Package 3- 100MLD WTP at Vasoorichira -Components 1.Cascade Aerator 2.Raw water channel 3.Flash mixer 4.Clarrifloculators 5.Filter House 6.Chemical House 7.Admin Building 8.Chlorine Building 9. Wash water Recovery tank 10.Sludge sump 11. Bypass channel 12.Connecting channels All component-related works were completed except external works including stormwater drain which was not done due to public protest. Kollam Project HD
05 Jan 2024 Packages 1, 4,,5 are completed and the package of 2 – Construction of weir at Njnkadavu across Kallada river – Work Re- Tendered with bid submission date as on 26/06/2023 and tender opening date as on 27-06-2023. Tender opened, two bidders participated. Prequalified by the STC. Price bid opened on 21/7/2023 and Submitted for negotiation to the contractor on 29/7/2023. After negotiation tender submitted to CE's office for sanction on 8/8/2023.Tender submitted to Government for sanction on 2/9/2023. Package 3- 100MLD WTP at Vasoorichira Components 1.Cascade Aerator 2.Raw water channel 3.Flash mixer 4.Clarrifloculators 5.Filter House 6.Chemical House 7.Admin Building 8.Chlorine Building 9. Wash water Recovery tank 10.Sludge sump 11. Bypass channel 12.Connecting channels All component-related works were completed except external works including stormwater drain which was not done due to public protest. Kollam Project HD
31 Dec 2023 Packages 1, 4,,5 are completed and the package of 2 – Construction of weir at Njnkadavu across Kallada river – Work Re- Tendered with bid submission date as on 26/06/2023 and tender opening date as on 27-06-2023. Tender opened, two bidders participated. Prequalified by the STC. Price bid opened on 21/7/2023 and Submitted for negotiation to the contractor on 29/7/2023. After negotiation tender submitted to CE's office for sanction on 8/8/2023.Tender submitted to Government for sanction on 2/9/2023. Package 3- 100MLD WTP at Vasoorichira- Components 1.Cascade Aerator 2.Raw water channel 3.Flash mixer 4.Clarrifloculators 5.Filter House 6.Chemical House 7.Admin Building 8.Chlorine Building 9. Wash water Recovery tank 10.Sludge sump 11. Bypass channel 12.Connecting channels All component-related works were completed except external works including stormwater drain which was not done due to public protest. Kollam Project HD
11 Dec 2023 Packages 1, 4,,5 are completed and the package of 2 – Construction of weir at Njnkadavu across Kallada river – Work tendered and last date of bid submission on 25/04/2023.Tender cancelled because of the non participation of bidders. Estimate recasted. Tendered with due date as on 29/05/2023.No offer received. Tender cancelled because of the non participation of bidders. Hence Re- Tendered with bid submission date as on 26/06/2023 and tender opening date as on 27-06-2023. Tender opened, two bidders participated. Prequalified by the STC. Price bid opened on 21/7/2023 and Submitted for negotiation to the contractor on 29/7/2023. After negotiation tender submitted to CE's office for sanction on 8/8/2023.Tender submitted to Government for sanction on 2/9/2023. Package 3- 100MLD WTP at Vasoorichira-All structural works up to walkway slab level completed. (c) CFL03 to filter house: All structural works up to slab at +8.75 level completed. Hydro test completed. Finishing work in progress Kollam Project Dn EE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 04/04/2018
Scheduled date of Completion of the Project 19 Jun 2020
Expected date of Completion 30/06/2023

Processing Dates

AS Date 12 Feb 2022
TS Date 07 Mar 2018

Other details

Project Officers View