Overall Project Status

Status Date Overall Project Status Project Officer Contact
11 Jan 2024 Packages 1, 4,,5 are completed and the package of 2 – Construction of weir at Njnkadavu across Kallada river – Work Re- Tendered with bid submission date as on 26/06/2023 and tender opening date as on 27-06-2023. Tender opened, two bidders participated. Prequalified by the STC. Price bid opened on 21/7/2023 and Submitted for negotiation to the contractor on 29/7/2023. After negotiation tender submitted to CE's office for sanction on 8/8/2023.Tender submitted to Government for sanction on 2/9/2023. Package 3- 100MLD WTP at Vasoorichira - Components 1.Cascade Aerator 2.Raw water channel 3.Flash mixer 4.Clarrifloculators 5.Filter House 6.Chemical House 7.Admin Building 8.Chlorine Building 9. Wash water Recovery tank 10.Sludge sump 11. Bypass channel 12.Connecting channels All component-related works were completed except external works including stormwater drain which was not done due to public protest. Kollam Project HD
10 Jan 2024 Packages 1, 4,,5 are completed and the package of 2 – Construction of weir at Njnkadavu across Kallada river – Work Re- Tendered with bid submission date as on 26/06/2023 and tender opening date as on 27-06-2023. Tender opened, two bidders participated. Prequalified by the STC. Price bid opened on 21/7/2023 and Submitted for negotiation to the contractor on 29/7/2023. After negotiation tender submitted to CE's office for sanction on 8/8/2023.Tender submitted to Government for sanction on 2/9/2023. Package 3- 100MLD WTP at Vasoorichira -Components 1.Cascade Aerator 2.Raw water channel 3.Flash mixer 4.Clarrifloculators 5.Filter House 6.Chemical House 7.Admin Building 8.Chlorine Building 9. Wash water Recovery tank 10.Sludge sump 11. Bypass channel 12.Connecting channels All component-related works were completed except external works including stormwater drain which was not done due to public protest. Kollam Project HD
05 Jan 2024 Packages 1, 4,,5 are completed and the package of 2 – Construction of weir at Njnkadavu across Kallada river – Work Re- Tendered with bid submission date as on 26/06/2023 and tender opening date as on 27-06-2023. Tender opened, two bidders participated. Prequalified by the STC. Price bid opened on 21/7/2023 and Submitted for negotiation to the contractor on 29/7/2023. After negotiation tender submitted to CE's office for sanction on 8/8/2023.Tender submitted to Government for sanction on 2/9/2023. Package 3- 100MLD WTP at Vasoorichira Components 1.Cascade Aerator 2.Raw water channel 3.Flash mixer 4.Clarrifloculators 5.Filter House 6.Chemical House 7.Admin Building 8.Chlorine Building 9. Wash water Recovery tank 10.Sludge sump 11. Bypass channel 12.Connecting channels All component-related works were completed except external works including stormwater drain which was not done due to public protest. Kollam Project HD
31 Dec 2023 Packages 1, 4,,5 are completed and the package of 2 – Construction of weir at Njnkadavu across Kallada river – Work Re- Tendered with bid submission date as on 26/06/2023 and tender opening date as on 27-06-2023. Tender opened, two bidders participated. Prequalified by the STC. Price bid opened on 21/7/2023 and Submitted for negotiation to the contractor on 29/7/2023. After negotiation tender submitted to CE's office for sanction on 8/8/2023.Tender submitted to Government for sanction on 2/9/2023. Package 3- 100MLD WTP at Vasoorichira- Components 1.Cascade Aerator 2.Raw water channel 3.Flash mixer 4.Clarrifloculators 5.Filter House 6.Chemical House 7.Admin Building 8.Chlorine Building 9. Wash water Recovery tank 10.Sludge sump 11. Bypass channel 12.Connecting channels All component-related works were completed except external works including stormwater drain which was not done due to public protest. Kollam Project HD
11 Dec 2023 Packages 1, 4,,5 are completed and the package of 2 – Construction of weir at Njnkadavu across Kallada river – Work tendered and last date of bid submission on 25/04/2023.Tender cancelled because of the non participation of bidders. Estimate recasted. Tendered with due date as on 29/05/2023.No offer received. Tender cancelled because of the non participation of bidders. Hence Re- Tendered with bid submission date as on 26/06/2023 and tender opening date as on 27-06-2023. Tender opened, two bidders participated. Prequalified by the STC. Price bid opened on 21/7/2023 and Submitted for negotiation to the contractor on 29/7/2023. After negotiation tender submitted to CE's office for sanction on 8/8/2023.Tender submitted to Government for sanction on 2/9/2023. Package 3- 100MLD WTP at Vasoorichira-All structural works up to walkway slab level completed. (c) CFL03 to filter house: All structural works up to slab at +8.75 level completed. Hydro test completed. Finishing work in progress Kollam Project Dn EE
06 Dec 2023 Packages 1, 4,,5 are completed and the package of 2 – Construction of weir at Njnkadavu across Kallada river – Work tendered and last date of bid submission on 25/04/2023.Tender cancelled because of the non participation of bidders. Estimate recasted. Tendered with due date as on 29/05/2023.No offer received. Tender cancelled because of the non participation of bidders. Hence Re- Tendered with bid submission date as on 26/06/2023 and tender opening date as on 27-06-2023. Tender opened, two bidders participated. Prequalified by the STC. Price bid opened on 21/7/2023 and Submitted for negotiation to the contractor on 29/7/2023. After negotiation tender submitted to CE's office for sanction on 8/8/2023.Tender submitted to Government for sanction on 2/9/2023. Package 3- 100MLD WTP at Vasoorichira – All structural works up to walkway slab level completed. (c) CFL03 to filter house: All structural works up to slab at +8.75 level completed. Hydro test completed. Finishing work in progress. Kollam Project Dn EE
05 Dec 2023 Packages 1, 4,,5 are completed and the package of 2 – Construction of weir at Njnkadavu across Kallada river – Selection notice was issued to the lowest tenderer at 10% above Estimate rate on 30-03-2022. The tenderer informed that he is not willing to execute the work at 10% above estimate rate. But he is willing to execute the work at their quoted rate of 29.80% above estimate rate. The superintending engineer submitted a recommendation letter to CE(SR) on 6/5/2022. Explaining necessity and important of work and also requested to taken up the matter at higher level for further directions. Taken up at Government level by MD on 24/05/2022. Tender rejected from Govt on 27/09/2022.Letter given to Irrigation department for recasting the estimate and recasted estimate from irrigation department on 8/11/22. Estimate prepared in price price 3 and submitted to higher office for approval. The estimate return back from CE's office for correction and Irrigation (mechanical wing) requested to add the centage charge in their estimate part and they submit the revised estimate on 16.1.2023 and Estimate prepared in Price 3.0 and submitted to higher office. Work tendered and last date of bid submission on 25/04/2023.Tender cancelled because of the non participation of bidders. Estimate recasted. Tendered with due date as on 29/05/2023.No offer received. Tender cancelled because of the non participation of bidders. Hence Re- Tendered with bid submission date as on 26/06/2023 and tender opening date as on 27-06-2023. Tender opened, two bidders participated. Prequalified by the STC. Price bid opened on 21/7/2023 and Submitted for negotiation to the contractor on 29/7/2023. After negotiation tender submitted to CE's office for sanction on 8/8/2023.Tender submitted to Government for sanction on 2/9/2023. Package 3- Design, Construction, Commissioning and maintaining of 100MLD WTP at Vasoorichira – 1)Cascade Aerator– All structural works up to +11.70lvl completed. Hydro testing completed. Finishing work in progress. (2)Raw water channel- All structural works up to +10.50lvl completed. Hydrotest completed. Finishing work in progress. (3)Flash mixer-All structural works up to +9.65lvl completed. Hydro test in progress. (4) Clariflocculators (4.a) CFL 1 – All structural work up to walkway slab at +9.05lvl completed. Hydrotest completed. Finishing work in progress. Erection of Bridge assly, scrapper unit, flocculator unit and rotation mechanism completed. Construction of valve chamber completed. (4.b) CFL 2 - All structural work up to walkway slab at +9.05lvl completed. Hydrotest completed. Finishing work in progress. Erection of Bridge assly, scrapper unit, flocculator unit and rotation mechanism completed. Construction of valve chamber completed. (4.c) CFL 3 - All structural work up to walkway slab at +9.05lvl completed. Hydrotest completed. Finishing work in progress. Erection of Bridge assly, scrapper unit, flocculator unit and rotation mechanism completed. Construction of valve chamber completed. (5) Filter House- All structural works up to +17.45m lvl completed. OHT hydrotest completed. Finishing work in progress. Hand rails fixing in progress. Erection for DI and MS pipes and valves in progress. Fixing of lateral pipes in progress. Windows and ventilation fixing in progress. Installation of EOT crane in pump house completed. CWR floor plastering completed. Air pipe erection in filter bed completed. Exterior painting in progress. Filter bed Hydro testing in progress. Filter media laying in progress. (6) Chemical House –All structural works up to +13.30lvl completed. Windows and ventilation fixing in progress. Gantry girder installation completed. Finishing work in progress. Electrical works in progress. (7) Admin Building-All structural works up to +12.8m lvl completed. Finishing, sanitary & electrical works in progress. Windows and ventilation fixing in progress. (8) Chlorine building – All structural works up to +9.625lvl completed. Exterior painting in progress. Windows and ventilation fixing in progress. Mono rail erection completed. Control valves and pumps erection in progress. (9) Back Wash Recovery tank- All structural works up to +4.50lvl completed. Plastering completed. Hand rails fixing completed. (10)Sludge sump - All structural works up to +10.125lvl completed. Finishing works in progress. Monorail erection completed. (11) Bypass channel - All structural works up to walkway slab level completed. Hydro testing in progress. Finishing works in progress. (12) Connecting channel (a) CFL01 to filter house: All structural works up to slab at +8.75 levels completed. Hydro test completed. Finishing work in progress. (b) CFL02 to filter house: All structural works up to walkway slab level completed. (c) CFL03 to filter house: All structural works up to slab at +8.75 level completed. Hydro test completed. Finishing work in progress. Kollam Project Dn EE
03 Dec 2023 Packages 1, 4,,5 are completed and the package of 2 – Construction of weir at Njnkadavu across Kallada river – Selection notice was issued to the lowest tenderer at 10% above Estimate rate on 30-03-2022. The tenderer informed that he is not willing to execute the work at 10% above estimate rate. But he is willing to execute the work at their quoted rate of 29.80% above estimate rate. The superintending engineer submitted a recommendation letter to CE(SR) on 6/5/2022. Explaining necessity and important of work and also requested to taken up the matter at higher level for further directions. Taken up at Government level by MD on 24/05/2022. Tender rejected from Govt on 27/09/2022.Letter given to Irrigation department for recasting the estimate and recasted estimate from irrigation department on 8/11/22. Estimate prepared in price price 3 and submitted to higher office for approval. The estimate return back from CE's office for correction and Irrigation (mechanical wing) requested to add the centage charge in their estimate part and they submit the revised estimate on 16.1.2023 and Estimate prepared in Price 3.0 and submitted to higher office. Work tendered and last date of bid submission on 25/04/2023.Tender cancelled because of the non participation of bidders. Estimate recasted. Tendered with due date as on 29/05/2023.No offer received. Tender cancelled because of the non participation of bidders. Hence Re- Tendered with bid submission date as on 26/06/2023 and tender opening date as on 27-06-2023. Tender opened, two bidders participated. Prequalified by the STC. Price bid opened on 21/7/2023 and Submitted for negotiation to the contractor on 29/7/2023. After negotiation tender submitted to CE's office for sanction on 8/8/2023.Tender submitted to Government for sanction on 2/9/2023. Package 3- Design, Construction, Commissioning and maintaining of 100MLD WTP at Vasoorichira – 1)Cascade Aerator– All structural works up to +11.70lvl completed. Hydro testing completed. Finishing work in progress. (2)Raw water channel- All structural works up to +10.50lvl completed. Hydrotest completed. Finishing work in progress. (3)Flash mixer-All structural works up to +9.65lvl completed. Hydro test in progress. (4) Clariflocculators (4.a) CFL 1 – All structural work up to walkway slab at +9.05lvl completed. Hydrotest completed. Finishing work in progress. Erection of Bridge assly, scrapper unit, flocculator unit and rotation mechanism completed. Construction of valve chamber completed. (4.b) CFL 2 - All structural work up to walkway slab at +9.05lvl completed. Hydrotest completed. Finishing work in progress. Erection of Bridge assly, scrapper unit, flocculator unit and rotation mechanism completed. Construction of valve chamber completed. (4.c) CFL 3 - All structural work up to walkway slab at +9.05lvl completed. Hydrotest completed. Finishing work in progress. Erection of Bridge assly, scrapper unit, flocculator unit and rotation mechanism completed. Construction of valve chamber completed. (5) Filter House- All structural works up to +17.45m lvl completed. OHT hydrotest completed. Finishing work in progress. Hand rails fixing in progress. Erection for DI and MS pipes and valves in progress. Fixing of lateral pipes in progress. Windows and ventilation fixing in progress. Installation of EOT crane in pump house completed. CWR floor plastering completed. Air pipe erection in filter bed completed. Exterior painting in progress. Filter bed Hydro testing in progress. Filter media laying in progress. (6) Chemical House –All structural works up to +13.30lvl completed. Windows and ventilation fixing in progress. Gantry girder installation completed. Finishing work in progress. Electrical works in progress. (7) Admin Building-All structural works up to +12.8m lvl completed. Finishing, sanitary & electrical works in progress. Windows and ventilation fixing in progress. (8) Chlorine building – All structural works up to +9.625lvl completed. Exterior painting in progress. Windows and ventilation fixing in progress. Mono rail erection completed. Control valves and pumps erection in progress. (9) Back Wash Recovery tank- All structural works up to +4.50lvl completed. Plastering completed. Hand rails fixing completed. (10)Sludge sump - All structural works up to +10.125lvl completed. Finishing works in progress. Monorail erection completed. (11) Bypass channel - All structural works up to walkway slab level completed. Hydro testing in progress. Finishing works in progress. (12) Connecting channel (a) CFL01 to filter house: All structural works up to slab at +8.75 levels completed. Hydro test completed. Finishing work in progress. (b) CFL02 to filter house: All structural works up to walkway slab level completed. (c) CFL03 to filter house: All structural works up to slab at +8.75 level completed. Hydro test completed. Finishing work in progress. Kollam Project Dn EE
01 Dec 2023 Packages 1, 4,,5 are completed and the package of 2 – Construction of weir at Njnkadavu across Kallada river – Selection notice was issued to the lowest tenderer at 10% above Estimate rate on 30-03-2022. The tenderer informed that he is not willing to execute the work at 10% above estimate rate. But he is willing to execute the work at their quoted rate of 29.80% above estimate rate. The superintending engineer submitted a recommendation letter to CE(SR) on 6/5/2022. Explaining necessity and important of work and also requested to taken up the matter at higher level for further directions. Taken up at Government level by MD on 24/05/2022. Tender rejected from Govt on 27/09/2022.Letter given to Irrigation department for recasting the estimate and recasted estimate from irrigation department on 8/11/22. Estimate prepared in price price 3 and submitted to higher office for approval. The estimate return back from CE's office for correction and Irrigation (mechanical wing) requested to add the centage charge in their estimate part and they submit the revised estimate on 16.1.2023 and Estimate prepared in Price 3.0 and submitted to higher office. Work tendered and last date of bid submission on 25/04/2023.Tender cancelled because of the non participation of bidders. Estimate recasted. Tendered with due date as on 29/05/2023.No offer received. Tender cancelled because of the non participation of bidders. Hence Re- Tendered with bid submission date as on 26/06/2023 and tender opening date as on 27-06-2023. Tender opened, two bidders participated. Prequalified by the STC. Price bid opened on 21/7/2023 and Submitted for negotiation to the contractor on 29/7/2023. After negotiation tender submitted to CE's office for sanction on 8/8/2023.Tender submitted to Government for sanction on 2/9/2023. Package 3- Design, Construction, Commissioning and maintaining of 100MLD WTP at Vasoorichira – 1)Cascade Aerator– All structural works up to +11.70lvl completed. Hydro testing completed. Finishing work in progress. (2)Raw water channel- All structural works up to +10.50lvl completed. Hydrotest completed. Finishing work in progress. (3)Flash mixer-All structural works up to +9.65lvl completed. Hydro test in progress. (4) Clariflocculators (4.a) CFL 1 – All structural work up to walkway slab at +9.05lvl completed. Hydrotest completed. Finishing work in progress. Erection of Bridge assly, scrapper unit, flocculator unit and rotation mechanism completed. Construction of valve chamber completed. (4.b) CFL 2 - All structural work up to walkway slab at +9.05lvl completed. Hydrotest completed. Finishing work in progress. Erection of Bridge assly, scrapper unit, flocculator unit and rotation mechanism completed. Construction of valve chamber completed. (4.c) CFL 3 - All structural work up to walkway slab at +9.05lvl completed. Hydrotest completed. Finishing work in progress. Erection of Bridge assly, scrapper unit, flocculator unit and rotation mechanism completed. Construction of valve chamber completed. (5) Filter House- All structural works up to +17.45m lvl completed. OHT hydrotest completed. Finishing work in progress. Hand rails fixing in progress. Erection for DI and MS pipes and valves in progress. Fixing of lateral pipes in progress. Windows and ventilation fixing in progress. Installation of EOT crane in pump house completed. CWR floor plastering completed. Air pipe erection in filter bed completed. Exterior painting in progress. Filter bed Hydro testing in progress. Filter media laying in progress. (6) Chemical House –All structural works up to +13.30lvl completed. Windows and ventilation fixing in progress. Gantry girder installation completed. Finishing work in progress. Electrical works in progress. (7) Admin Building-All structural works up to +12.8m lvl completed. Finishing, sanitary & electrical works in progress. Windows and ventilation fixing in progress. (8) Chlorine building – All structural works up to +9.625lvl completed. Exterior painting in progress. Windows and ventilation fixing in progress. Mono rail erection completed. Control valves and pumps erection in progress. (9) Back Wash Recovery tank- All structural works up to +4.50lvl completed. Plastering completed. Hand rails fixing completed. (10)Sludge sump - All structural works up to +10.125lvl completed. Finishing works in progress. Monorail erection completed. (11) Bypass channel - All structural works up to walkway slab level completed. Hydro testing in progress. Finishing works in progress. (12) Connecting channel (a) CFL01 to filter house: All structural works up to slab at +8.75 levels completed. Hydro test completed. Finishing work in progress. (b) CFL02 to filter house: All structural works up to walkway slab level completed. (c) CFL03 to filter house: All structural works up to slab at +8.75 level completed. Hydro test completed. Finishing work in progress. up to slab at +8.75 levels completed. Hydro test completed. Finishing work in progress. (b) CFL02 to filter house: All structural works up to walkway slab level completed. (c) CFL03 to filter house: All structural works up to slab at +8.75 level completed. Hydro test completed. Finishing work in progress. Kollam Project Dn EE
28 Nov 2023 Packages 1, 4,,5 are completed and the package of 2 - Construction of weir at Njnkadavu across Kallada river - Selection notice was issued to the lowest tenderer at 10% above Estimate rate on 30-03-2022. The tenderer informed that he is not willing to execute the work at 10% above estimate rate. But he is willing to execute the work at their quoted rate of 29.80% above estimate rate. The superintending engineer submitted a recommendation letter to CE(SR) on 6/5/2022. Explaining necessity and important of work and also requested to taken up the matter at higher level for further directions. Taken up at Government level by MD on 24/05/2022. Tender rejected from Govt on 27/09/2022.Letter given to Irrigation department for recasting the estimate and recasted estimate from irrigation department on 8/11/22. Estimate prepared in price price 3 and submitted to higher office for approval.The estimate return back from CE's office for correction and Irrigation (mechanical wing) requested to add the centage charge in their estimate part and they submit the revised estimate on 16.1.2023 and Estimate prepared in Price 3.0 and submitted to higher office. Work tendered and last date of bid submission on 25/04/2023.Tender cancelled because of the non participation of bidders. Estimate recasted. Tendered with due date as on 29/05/2023.No offer received. Tender cancelled because of the non participation of bidders. Hence Re- Tendered with bid submission date as on 26/06/2023 and tender opening date as on 27-06-2023. Tender opened, two bidders participated. Prequalified by the STC. Price bid opened on 21/7/2023 and Submitted for negotiation to the contractor on 29/7/2023. After negotiation tender submitted to CE's office for sanction on 8/8/2023.Tender submitted to Government for sanction on 2/9/2023.Package 3- Design, Construction, Commissioning and maintaining of 100MLD WTP at Vasoorichira – 1)Cascade Aerator– All structural works up to +11.70lvl completed. Hydro testing completed. Finishing work in progress. (2)Raw water channel- All structural works up to +10.50lvl completed. Hydrotest completed. Finishing work in progress. (3)Flash mixer-All structural works up to +9.65lvl completed. Hydro test in progress. (4) Clariflocculators (4.a) CFL 1 – All structural work up to walkway slab at +9.05lvl completed. Hydrotest completed. Finishing work in progress. Erection of Bridge assly, scrapper unit, flocculator unit and rotation mechanism completed. Construction of valve chamber completed. (4.b) CFL 2 - All structural work up to walkway slab at +9.05lvl completed. Hydrotest completed. Finishing work in progress. Erection of Bridge assly, scrapper unit, flocculator unit and rotation mechanism completed. Construction of valve chamber completed. (4.c) CFL 3 - All structural work up to walkway slab at +9.05lvl completed. Hydrotest completed. Finishing work in progress. Erection of Bridge assly, scrapper unit, flocculator unit and rotation mechanism completed. Construction of valve chamber completed. (5) Filter House- All structural works up to +17.45m lvl completed. OHT hydrotest completed. Finishing work in progress. Hand rails fixing in progress. Erection for DI and MS pipes and valves in progress. Fixing of lateral pipes in progress. Windows and ventilation fixing in progress. Installation of EOT crane in pump house completed. CWR floor plastering completed. Air pipe erection in filter bed completed. Exterior painting in progress. Filter bed Hydro testing in progress. Filter media laying in progress. (6) Chemical House –All structural works up to +13.30lvl completed. Windows and ventilation fixing in progress. Gantry girder installation completed. Finishing work in progress. Electrical works in progress. (7) Admin Building-All structural works up to +12.8m lvl completed. Finishing, sanitary & electrical works in progress. Windows and ventilation fixing in progress. (8) Chlorine building – All structural works up to +9.625lvl completed. Exterior painting in progress. Windows and ventilation fixing in progress. Mono rail erection completed. Control valves and pumps erection in progress. (9) Back Wash Recovery tank- All structural works up to +4.50lvl completed. Plastering completed. Hand rails fixing completed. (10)Sludge sump - All structural works up to +10.125lvl completed. Finishing works in progress. Monorail erection completed. (11) Bypass channel - All structural works up to walkway slab level completed. Hydro testing in progress. Finishing works in progress. (12) Connecting channel (a) CFL01 to filter house: All structural works up to slab at +8.75 levels completed. Hydro test completed. Finishing work in progress. (b) CFL02 to filter house: All structural works up to walkway slab level completed. (c) CFL03 to filter house: All structural works up to slab at +8.75 level completed. Hydro test completed. Finishing work in progress. Kollam Project HD