| Project | Supplying laying commissioning and maintaining 500mm DI K9 CWPM from TP to OHSR at Vadakkevila (3520m) SAAP YEAR 2015-16) |
|---|---|
| Project Code | KLMGOI0917464P1 |
| Type | Package |
| Main Project | 22 AMRUT ATAL MISSION FOR REJUVENATION AND URBAN TRA(75)-AMRUT-Augmentation of WSS in Kollam Corporation(8518) |
| Funding Agency | AMRUT |
| Category | AMRUT |
| Type of scheme | Water Supply |
| Scheme | AMRUT |
| Description | Supplying laying commissioning and maintaining 500mm DI K9 CWPM from TP to OHSR at Vadakkevila (3520m) T S Amount RS.43310000 (4.3310 crore) |
| Status | On-going |
| District | Kollam |
| Executing Office | Kollam Project Dn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 43310000 |
| TS Number | TS/2017-2018/2017/4018 dtd 15.12.2017 |
| Technical specification | Supplying laying commissioning and maintaining 500mm DI K9 CWPM from TP to OHSR at Vadakkevila (3520m) |
| Contractor | Veluswami Subbayya (Mob: 9176118881) |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 10/01/2019 |
|---|---|
| Scheduled date of Completion as per agreement | 09 Jan 2020 |
| Expected date of Completion | 31/12/2020 |
| TS Date | 15 Dec 2017 |
|---|---|
| Estimate Approval | 15 Dec 2017 |
| NIT Approval | 20 Dec 2017 |
| Tender Closing | 19 Apr 2018 |
| Technichal Pre-Qualification | 07 Apr 2018 |
| Price bid opening | 21 Apr 2018 |
| NA | 25 Mar 2021 |
|---|---|
| Workorder Date | 05 Jan 2019 |
| Kollam Project HD |
| Date: 14/12/2021 |
Work has been completed | 100% Completed
Work completed .
| Kollam Project HD |
| Date: 04/12/2021 |
Work has been completed | 100% Completed
Completed .