Supplying laying commissioning and maintaining 500mm DI K9 CWPM from TP to OHSR at Vadakkevila (3520m) SAAP YEAR 2015-16)

Project Supplying laying commissioning and maintaining 500mm DI K9 CWPM from TP to OHSR at Vadakkevila (3520m) SAAP YEAR 2015-16)
Project Code KLMGOI0917464P1
Type Package
Main Project 22 AMRUT ATAL MISSION FOR REJUVENATION AND URBAN TRA(75)-AMRUT-Augmentation of WSS in Kollam Corporation(8518)
Funding Agency AMRUT
Category AMRUT
Type of scheme Water Supply
Scheme AMRUT
Description Supplying laying commissioning and maintaining 500mm DI K9 CWPM from TP to OHSR at Vadakkevila (3520m) T S Amount RS.43310000 (4.3310 crore)
Status On-going
District Kollam
Executing Office Kollam Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 43310000
TS Number TS/2017-2018/2017/4018 dtd 15.12.2017
Technical specification Supplying laying commissioning and maintaining 500mm DI K9 CWPM from TP to OHSR at Vadakkevila (3520m)
Contractor Veluswami Subbayya (Mob: 9176118881)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 10/01/2019
Scheduled date of Completion as per agreement 09 Jan 2020
Expected date of Completion 31/12/2020

Processing Dates

TS Date 15 Dec 2017
Estimate Approval 15 Dec 2017
NIT Approval 20 Dec 2017
Tender Closing 19 Apr 2018
Technichal Pre-Qualification 07 Apr 2018
Price bid opening 21 Apr 2018

Approval Dates

NA 25 Mar 2021
Workorder Date 05 Jan 2019

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kollam Project HD
Date: 14/12/2021

Work has been completed | 100% Completed

Work completed .

Kollam Project HD
Date: 04/12/2021

Work has been completed | 100% Completed

Completed .