Project | AMRUT-Integrated Calicut Water Supply Project Phase-2,Laying Diistribution Lines in Elathur Zone |
---|---|
Project Code | CLTGOI0118511P10 |
Type | Package |
Main Project | AMRUT-Integrated Calicut Water Supply Project Phase-2,Laying Distribution Lines in 10 Zone in Kozhikode corporation |
Funding Agency | AMRUT |
Category | AMRUT |
Type of scheme | Water Supply |
Scheme | AMRUT |
Description | AMRUT-Integrated Calicut Water Supply Project Phase-2,Laying Diistribution Lines in Elathur Zone |
Status | Completed |
District | Kozhikkode |
Executing Office | Kozhikode Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 16000000 |
TS Number | TS/3004/2018-2019 |
Technical specification | Scope of Work- Supplying and Laying- 75mm PVC pipe 16393 80 mm GI Pipe 300 |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 20/02/2019 |
---|---|
Scheduled date of Completion as per agreement | 27 Jul 2019 |
Expected date of Completion | 31/12/2020 |
AS Date | 01 Jan 2018 |
---|---|
TS Date | 22 Nov 2018 |
Estimate Approval | 22 Nov 2018 |
NIT Approval | 23 Nov 2018 |
Tender Closing | 20 Dec 2018 |
Price bid opening | 24 Dec 2018 |
CE Approval | 09 Jan 2019 |
---|---|
Final Approval | 09 Jan 2019 |
Workorder Date | 28 Jan 2019 |
NA | 20 Feb 2019 |
Kozhikode Project Dn AE5 |
Date: 22/09/2021 |
Work has been completed | 100% Completed
Work completed, Total expenditure Rs.8302915/- final Bill paid to contractor on 27-07-2021including Road restoration charges ..
Kozhikode Project Dn AE5 |
Date: 17/08/2021 |
Work has been completed | 100% Completed
work completed.