Kozhikode Project Dn AE5 |
Date: 22/09/2021 |
Work has been completed | 100% Completed
Work completed, Total expenditure Rs.8302915/- final Bill paid to contractor on 27-07-2021including Road restoration charges .
Kozhikode Project Dn AE5 |
Date: 17/08/2021 |
Work has been completed | 100% Completed
work completed
Kozhikode Project Dn AE2 |
Date: 21/04/2021 |
Work has been completed | 100% Completed
Work completed. Final Bill submitted
Kozhikode Project Dn AE2 |
Date: 19/04/2021 |
Work has been completed | 100% Completed
Work completed. Final Bill submitted
Kozhikode Project Dn AE2 |
Date: 17/04/2021 |
Work has been completed | 100% Completed
Work completed. Final Bill submitted
Kozhikode Project Dn AE2 |
Date: 15/04/2021 |
Work has been completed | 100% Completed
Work completed. Final Bill submitted
Kozhikode Project Dn AE2 |
Date: 12/04/2021 |
Work has been completed | 100% Completed
Work completed. Final Bill submitted
Kozhikode Project Dn AE2 |
Date: 08/04/2021 |
Work has been completed | 100% Completed
Work completed. Final Bill submitted
Kozhikode Project Dn AE2 |
Date: 07/04/2021 |
Work has been completed | 100% Completed
Work completed. Final Bill submitted
Kozhikode Project Dn AE2 |
Date: 05/04/2021 |
Work has been completed | 100% Completed
Work completed. Final Bill submitted
Kozhikode Project Dn AE2 |
Date: 03/04/2021 |
Work has been completed | 100% Completed
Work completed. Final Bill submitted
Kozhikode Project Dn AE2 |
Date: 31/03/2021 |
Work has been completed | 100% Completed
Work completed. Final Bill submitted
Kozhikode Project Dn AE2 |
Date: 29/03/2021 |
Work has been completed | 100% Completed
Work completed. Final Bill submitted
Kozhikode Project Dn AE2 |
Date: 27/03/2021 |
Work has been completed | 100% Completed
Work completed. Final Bill submitted
Kozhikode Project Dn AE2 |
Date: 26/03/2021 |
Work has been completed | 100% Completed
Work completed. Final Bill submitted
Kozhikode Project Dn AE2 |
Date: 25/03/2021 |
Work has been completed | 100% Completed
work has been completed, Final bill submitted
Kozhikode Project Dn AE2 |
Date: 23/03/2021 |
Work has been completed | 100% Completed
work has been completed, Final bill submitted
Kozhikode Project Dn AE2 |
Date: 18/03/2021 |
Work has been completed | 100% Completed
work has been completed, Final bill submitted
Kozhikode Project Dn AE2 |
Date: 15/03/2021 |
Work has been completed | 100% Completed
work has been completed, Final bill submitted
Kozhikode Project Dn AE2 |
Date: 08/03/2021 |
Work has been completed | 100% Completed
work completed, Final bill submitted
Kozhikode Project Dn AE2 |
Date: 03/03/2021 |
Work has been completed | 100% Completed
work completed, Final bill submitted
Kozhikode Project Dn AE2 |
Date: 23/02/2021 |
Work has been completed | 100% Completed
work completed final bill submitted
Kozhikode Project Dn AE2 |
Date: 29/01/2021 |
Work has been completed | 100% Completed
Final Bill amounting to RS 25,87,213/- prepared and submitted
Kozhikode Project Dn AE2 |
Date: 04/01/2021 |
Work has been completed | 100% Completed
Completed on 01.01.2021. Bill under preperation.
Kozhikode Project Dn AE2 |
Date: 09/11/2020 |
Work in progress | 99% Completed
Laying of distribution lines, fixing of line valves and air valves and road restoration work completed. Interconnection work in progress. All the pipe lines laid in this project are extensions of JICA distribution network. No pipe lines laid under AMRUT in Elathur zone is charged since charging and commissioning of JICA lines are not carried out since the distribution main is not connected to Tank due to land issue at Stephen Kunnu.
Attached images
Kozhikode Project Dn AE2 |
Date: 14/09/2020 |
Work in progress | 97% Completed
All pipes and specials supplied and laying completed. Restoration work completed. Fixing of line valves and air valves in progress. The distribution lines proposed under this project are extensions of JICA distribution network. But since JICA work is not completed and charged , the lines laid under AMRUT also could not be charged and commissioned.
Attached images
Kozhikode Project Dn AE2 |
Date: 18/08/2020 |
Work in progress | 96% Completed
All pipes and specials supplied and laying completed. Charging and commissioning - nil ( All the distribution network proposed under this project are extensions of JICA project- Elathur zone. As the inreconnection of tank with JICA distribribution main cannot be done due to land issue at Stephen Kunnu, charging and commissioning of AMRUT lines cannot be done)
Kozhikode Project Dn AE2 |
Date: 16/08/2020 |
Work in progress | 95% Completed
Laid length - 16000m (Out of 16393m) Commissioned length - Nil ( All the distribution network proposed are the extensions of JICA project - Elathur zone. The JICA distribution network is not charged, since the tank interconnection with distribution main cannot be executed due to land issue at Stephen kunnu. Hence the AMRUT distribution network.)
Kozhikode Project Dn AE2 |
Date: 01/07/2020 |
Work in progress | 90% Completed
Laid length - 15800m (Out of 16393m) Commissioned length - Nil ( All the distribution network proposed are the extensions of JICA project - Elathur zone. Since the tank interconnection cannot be executed due to land issue at Stephen kunnu, the JICA distribution network is not charged. Hence the AMRUT distribution network.)