AMRUT-Integrated Calicut Water Supply Project Phase-2,Laying Distribution Lines in 10 Zone in Kozhikode corporation
Project |
AMRUT-Integrated Calicut Water Supply Project Phase-2,Laying Distribution Lines in 10 Zone in Kozhikode corporation |
Project Code |
CLTGOI0118511 |
Type |
Main project |
Funding Agency |
AMRUT |
Category |
AMRUT |
Type of scheme |
Water Supply |
Scheme |
AMRUT |
Description |
AMRUT-Integrated Calicut Water Supply Project Phase-2, Laying Distribution Lines in 10 Zone in Kozhikode corporation
Intake well - Peruvannamuzhi (JICA )
Water Treatment plant - 174MLD at Peruvannamuzhi
|
Status |
Completed |
District |
Kozhikkode |
Executing Office |
Kozhikode Project Dn |
AS Amount (Rs) |
465500000
|
AS Number |
A.S.NO.GO.(Rt)NO.5/2018/LSGD |
TS Amount (Rs) |
416400000 |
TS Number |
TS/1900/2018-2019 ,TS/3006/2018-2019, TS/3007/2018-2019, TS/3008/2018-2019, |
Total Bill Submitted (Rs) |
358077348 |
Total Bill Paid (Rs) |
358077348 |
Population Benefitted |
700929 |
Capacity in MLD |
174.00 |
Actual Project Completion Date |
31 Mar 2021 |
Coverage |
Kozhikode corporation area
1.beypore zone
2.Cheruvanoor Zone
3.Eravathukunnu south Zone
4.Pottammal Zone
5.Eravathukunnu North Zone.
6.Balamandiram Zone
7.Easthill Zone
8.Malaparamba zone
9.Kovoor Zone
10.Elathur Zone.
|
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
AMRUT-Integrated Calicut Water Supply Project Phase-2,Laying Diistribution Lines in Balamandiram Zone |
Kozhikode Project Dn |
|
2 |
AMRUT-Integrated Calicut Water Supply Project Phase-2,Laying Diistribution Lines in Beypore Zone |
Kozhikode Project Dn |
|
3 |
AMRUT-Integrated Calicut Water Supply Project Phase-2,Laying Diistribution Lines in cheruvanoor zone |
Kozhikode Project Dn |
|
4 |
AMRUT-Integrated Calicut Water Supply Project Phase-2,Laying Diistribution Lines in East Hill Zone |
Kozhikode Project Dn |
|
5 |
AMRUT-Integrated Calicut Water Supply Project Phase-2,Laying Diistribution Lines in Elathur Zone |
Kozhikode Project Dn |
|
6 |
AMRUT-Integrated Calicut Water Supply Project Phase-2,Laying Diistribution Lines in Eravathukunnu North Zone |
Kozhikode Project Dn |
|
7 |
AMRUT-Integrated Calicut Water Supply Project Phase-2,Laying Diistribution Lines in Eravathukunnu South zone |
Kozhikode Project Dn |
|
8 |
AMRUT-Integrated Calicut Water Supply Project Phase-2,Laying Diistribution Lines in Kovoor Zone |
Kozhikode Project Dn |
|
9 |
AMRUT-Integrated Calicut Water Supply Project Phase-2,Laying Diistribution Lines in Malaparamba Zone |
Kozhikode Project Dn |
|
10 |
AMRUT-Integrated Calicut Water Supply Project Phase-2,Laying Diistribution Lines in Pottamel Zone |
Kozhikode Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
09 Nov 2021 |
"Beypore Zone- Work completed, Total expenditure Rs.88373299/- final Bill paid to contractor on 16-10-2020 including Road restoration charges .Pottamel Zone-Work completed, Total expenditure Rs.40652452/- final Bill paid to contractor on 26.02.2021 including Road restoration charges .Eravathukunnu South zone- Work completed, Total expenditure Rs.41077128/- final Bill paid to contractor on 06-02-2021 including Road restoration charges .Eravathukunnu North Zone- Work completed, Total expenditure Rs.12012960/- final Bill paid to contractor on 30.01.2021 including Road restoration charges .cheruvanoor zone- Work completed, Total expenditure Rs.16081647/- final Bill paid to contractor on 14.10.2020 including Road restoration charges .Elathur Zone- Work completed, Total expenditure Rs.8302915/- final Bill paid to contractor on 27-07-2021including Road restoration charges .Malaparamba Zone- Work completed, Total expenditure Rs.47922819/- final Bill paid to contractor on 27.07.2021 including Road restoration charges .Kovoor Zone- Work completed, Total expenditure Rs.57116895/- final Bill paid to contractor on 06.01.2021 including Road restoration charges .East Hill Zone- Work completed, Total expenditure Rs.36373563/- final Bill paid to contractor on 27.07.2021 including Road restoration charges .Balamandiram Zone- Work completed, Total expenditure Rs.10163670/- final Bill paid to contractor on 14.10.2020 including Road restoration charges . |
Kozhikode Project Dn AE5 |
|
22 Sep 2021 |
"Beypore Zone- Work completed, Total expenditure Rs.45514720/- final Bill paid to contractor on 16-10-2020 including Road restoration charges .Pottamel Zone-Work completed, Total expenditure Rs.40652452/- final Bill paid to contractor on 26.02.2021 including Road restoration charges .Eravathukunnu South zone- Work completed, Total expenditure Rs.36936365/- final Bill paid to contractor on 06-02-2021 including Road restoration charges .Eravathukunnu North Zone- Work completed, Total expenditure Rs.12012960/- final Bill paid to contractor on 30.01.2021 including Road restoration charges .cheruvanoor zone- Work completed, Total expenditure Rs.16081647/- final Bill paid to contractor on 14.10.2020 including Road restoration charges .Elathur Zone- Work completed, Total expenditure Rs.8302915/- final Bill paid to contractor on 27-07-2021including Road restoration charges .Malaparamba Zone- Work completed, Total expenditure Rs.47922819/- final Bill paid to contractor on 27.07.2021 including Road restoration charges .Kovoor Zone- Work completed, Total expenditure Rs.57116895/- final Bill paid to contractor on 06.01.2021 including Road restoration charges .East Hill Zone- Work completed, Total expenditure Rs.36373563/- final Bill paid to contractor on 27.07.2021 including Road restoration charges .Balamandiram Zone- Work completed, Total expenditure Rs.10163670/- final Bill paid to contractor on 14.10.2020 including Road restoration charges .
|
Kozhikode Project Dn AE5 |
|
20 Apr 2021 |
WORK COMPLETED |
Kozhikode Project Dn AE2 |
|
31 Mar 2021 |
WORK COMPLETED |
Kozhikode Project Dn AE2 |
|
19 Jun 2020 |
ON GOING |
Kozhikode Project Dn AE2 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
08/11/2018 |
Scheduled date of Completion of the Project |
09 Feb 2020 |
Expected date of Completion |
16/03/2021 |
Processing Dates
AS Date |
01 Jan 2018 |
TS Date |
19 Jul 2018 |