Project | AMRUT-Integrated Calicut Water Supply Project Phase-2,Laying Diistribution Lines in Eravathukunnu South zone |
---|---|
Project Code | CLTGOI0118511P3 |
Type | Package |
Main Project | AMRUT-Integrated Calicut Water Supply Project Phase-2,Laying Distribution Lines in 10 Zone in Kozhikode corporation |
Funding Agency | AMRUT |
Category | AMRUT |
Type of scheme | Water Supply |
Scheme | AMRUT |
Description | AMRUT-Integrated Calicut Water Supply Project Phase-2,Laying Diistribution Lines in Eravathukunnu South zone |
Status | Completed |
District | Kozhikkode |
Executing Office | Kozhikode Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 47100000 |
TS Number | TS/2151/2018-2019 |
Technical specification | Scope of work-Supplying and Laying 110mm PVC pipe -40339 100mm GI Pipe-500 |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 30/11/2018 |
---|---|
Scheduled date of Completion as per agreement | 13 Nov 2019 |
Expected date of Completion | 15/02/2021 |
TS Date | 03 Oct 2018 |
---|---|
Estimate Approval | 03 Oct 2018 |
NIT Approval | 04 Oct 2018 |
Tender Closing | 29 Oct 2018 |
Price bid opening | 01 Nov 2018 |
Workorder Date | 14 Nov 2018 |
---|---|
NA | 30 Nov 2018 |
Kozhikode Project Dn AE5 |
Date: 25/09/2021 |
Work has been completed | 100% Completed
Work completed, Total expenditure Rs.41077128/- final Bill paid to contractor on 06-02-2021 including Road restoration charges ..
Kozhikode Project Dn AE5 |
Date: 22/09/2021 |
Work has been completed | 100% Completed
Work completed, Total expenditure Rs.36936365/- final Bill paid to contractor on 06-02-2021 including Road restoration charges ..