Kozhikode Project Dn AE5 |
Date: 25/09/2021 |
Work has been completed | 100% Completed
Work completed, Total expenditure Rs.41077128/- final Bill paid to contractor on 06-02-2021 including Road restoration charges .
Kozhikode Project Dn AE5 |
Date: 22/09/2021 |
Work has been completed | 100% Completed
Work completed, Total expenditure Rs.36936365/- final Bill paid to contractor on 06-02-2021 including Road restoration charges .
Kozhikode Project Dn AE5 |
Date: 10/08/2021 |
Work has been completed | 100% Completed
work completed
Kozhikode Project Dn AE2 |
Date: 21/04/2021 |
Work has been completed | 100% Completed
work completed, final bill under preparation.
Kozhikode Project Dn AE2 |
Date: 19/04/2021 |
Work has been completed | 100% Completed
work completed, final bill under preparation.
Kozhikode Project Dn AE2 |
Date: 17/04/2021 |
Work has been completed | 100% Completed
work completed, final bill under preparation.
Kozhikode Project Dn AE2 |
Date: 15/04/2021 |
Work has been completed | 100% Completed
work completed, final bill under preparation.
Kozhikode Project Dn AE2 |
Date: 12/04/2021 |
Work has been completed | 100% Completed
work completed, final bill under preparation.
Kozhikode Project Dn AE2 |
Date: 08/04/2021 |
Work has been completed | 100% Completed
work completed, final bill under preparation.
Kozhikode Project Dn AE2 |
Date: 07/04/2021 |
Work has been completed | 100% Completed
work completed, final bill under preparation.
Kozhikode Project Dn AE2 |
Date: 05/04/2021 |
Work has been completed | 100% Completed
work completed, final bill under preparation.
Kozhikode Project Dn AE2 |
Date: 03/04/2021 |
Work has been completed | 100% Completed
work completed, final bill under preparation.
Kozhikode Project Dn AE2 |
Date: 31/03/2021 |
Work has been completed | 100% Completed
work completed, final bill under preparation.
Kozhikode Project Dn AE2 |
Date: 29/03/2021 |
Work has been completed | 100% Completed
work completed, final bill under preparation.
Kozhikode Project Dn AE2 |
Date: 27/03/2021 |
Work has been completed | 100% Completed
work completed, final bill under preparation
Kozhikode Project Dn AE2 |
Date: 25/03/2021 |
Work has been completed | 100% Completed
work completed, final bill under preparation
Kozhikode Project Dn AE2 |
Date: 23/03/2021 |
Work in progress | 99% Completed
Work in progress
Kozhikode Project Dn AE2 |
Date: 18/03/2021 |
Work in progress | 99% Completed
Work in progress
Kozhikode Project Dn AE2 |
Date: 15/03/2021 |
Work in progress | 99% Completed
Work in progress
Kozhikode Project Dn AE2 |
Date: 08/03/2021 |
Work in progress | 99% Completed
Work in progress
Kozhikode Project Dn AE2 |
Date: 03/03/2021 |
Work in progress | 99% Completed
Work in progress
Kozhikode Project Dn AE2 |
Date: 23/02/2021 |
Work in progress | 99% Completed
work in progress
Kozhikode Project Dn AE2 |
Date: 16/02/2021 |
Work in progress | 99% Completed
work in progress
Kozhikode Project Dn AE2 |
Date: 05/02/2021 |
Work in progress | 99% Completed
Road Reformation work in preogress
Kozhikode Project Dn AE2 |
Date: 26/11/2020 |
Work in progress | 99% Completed
Interconnection &pipe line charging work under progress and BT &CC road reformation work in progress. Total length of pipes: 110mm PVC pipe- 40339m and 100mm GI pipe 500m) Balance work 1. pipe line charrging and commissioning - 2km 2.Interconnection work- 22 nos 3.BT road reformation work- 6km 4.CC road reformation work- 500m PAC amount-4.54 cr Quoted PAC- 4.35cr Bill amount submitted-2.64 cr
Kozhikode Project Dn AE2 |
Date: 10/11/2020 |
Work in progress | 98% Completed
Interconnection &pipe line charging work under progress and BT &CC road reformation work in progress. Total length of pipes: 110mm PVC pipe- 40339m and 100mm GI pipe 500m) Balance work 1. pipe line charrging and commissioning - 4km 2.Interconnection work- 30 nos 3.BT road reformation work- 4km 4.CC road reformation work- 1km
Attached images
Kozhikode Project Dn AE2 |
Date: 12/10/2020 |
Work in progress | 97% Completed
Pipe Laying completed. Interconnection and road reformation work in progress (BT road 2km, Concrete road 3km, 27 nos of interconnection and 3.2km pipe line charging work are to be done) Total length of pipes: 110mm PVC pipe- 40339m and 100mm GI pipe 500m)
Attached images
Kozhikode Project Dn AE2 |
Date: 09/09/2020 |
Work in progress | 96% Completed
Pipe Laying completed. Interconnection and road reformation work in progress (BT road 2km, Concrete road 3.5km, 30 nos of interconnection and 3.5km pipe line charging work are to be done) Total length of pipes: 110mm PVC pipe- 40339m and 100mm GI pipe 500m)
Attached images
Kozhikode Project Dn AE2 |
Date: 17/08/2020 |
Work in progress | 95% Completed
Pipe Laying completed. Interconnection and road reformation work in progress (BT road 2km, Concrete road 4km, 40 nos of interconnection and 5km pipe line charging work are to be done) Total length of pipes: 110mm PVC pipe- 40339m and 100mm GI pipe 500m)
Kozhikode Project Dn AE2 |
Date: 14/08/2020 |
Work in progress | 94% Completed
Supplying Laying and Testing of -110mm pvc pipe-38500m out of 40339m,100mm Gi pipe 350m out of 500m, Road restoration work in progress
Kozhikode Project Dn AE2 |
Date: 01/07/2020 |
Work in progress | 93% Completed
Supplying Laying and Testing of -110mm pvc pipe-37650m out of 40339m,100mm Gi pipe 350m out of 500m