Deposit work (2021-2022) -ARWSS To Ambalavayal- Pipe line Extension to Various Places in Ambalavayal Grama Panchayat

Project Deposit work (2021-2022) -ARWSS To Ambalavayal- Pipe line Extension to Various Places in Ambalavayal Grama Panchayat
Project Code WYDDEPO032212066
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description Deposit work (2021-2022) -ARWSS To Ambalavayal- Pipe line Extension to Various Places in Ambalavayal Grama Panchayat
Status Completed
District Wayanad
Executing Office Sulthan Bathery Sn
AS Amount (Rs) 450000
AS Number A2-462/21
TS Amount (Rs) 450000
TS Number TS/2022-2023/2022/3238 Dated 14-07-2022
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 200
Capacity in MLD 10.00
Actual Project Completion Date Date is not specified
Coverage 70 LPCD
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Deposit work (2021-2022) -ARWSS To Ambalavayal- Pipe line Extension to Karimamkunnu-Ambalamkavu in Ambalavayal Grama Panchayat Sulthan Bathery Sn
2 Deposit work (2021-2022) -ARWSS To Ambalavayal- Pipe line Extension to Nellissery Shaji's house in Ambalavayal Grama Panchayat Sulthan Bathery Sn
3 Deposit work (2021-2022) -ARWSS To Ambalavayal- Pipe line Extension to Puthiyapadi Colony in Ambalavayal Grama Panchayat Sulthan Bathery Sn
4 Deposit work (2021-2022) -ARWSS To Ambalavayal- Pipe line Extension to Secretary Kavala in Ambalavayal Grama Panchayat Sulthan Bathery Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
26 Oct 2022 work completed Sulthan Bathery PH Sn - AE
22 Oct 2022 work in progress Sulthan Bathery PH Sn - AE
17 Oct 2022 work in progress Sulthan Bathery PH Sn - AE
14 Oct 2022 work in progress Sulthan Bathery PH Sn - AE
11 Oct 2022 work in progress Sulthan Bathery PH Sn - AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 14/07/2022
Scheduled date of Completion of the Project 25 Nov 2022
Expected date of Completion 25/11/2022

Processing Dates

AS Date 25 Mar 2022
TS Date 14 Jul 2022

Other details

Project Officers View