Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
26 Oct 2022 | work completed | Sulthan Bathery PH Sn - AE | |
22 Oct 2022 | work in progress | Sulthan Bathery PH Sn - AE | |
17 Oct 2022 | work in progress | Sulthan Bathery PH Sn - AE | |
14 Oct 2022 | work in progress | Sulthan Bathery PH Sn - AE | |
11 Oct 2022 | work in progress | Sulthan Bathery PH Sn - AE | |
01 Oct 2022 | pipes to be supplied by the contractor | Sulthan Bathery PH Sn - AE | |
01 Oct 2022 | plpes to be supplied by the contractor | Sulthan Bathery PH Sn - AE | |
19 Sep 2022 | Pipes to be supplied by the contractor | Sulthan Bathery PH Dn EE | |
06 Sep 2022 | Work order issued. Agreement to be executed | Sulthan Bathery PH Dn EE | |
30 Aug 2022 | Work order issued. Agreement to be executed | Sulthan Bathery PH Dn EE |