AMRUT 2.0-Angamaly Muncipality

Project AMRUT 2.0-Angamaly Muncipality
Project Code EKMAMRUT 2112214147
Type Main project
Funding Agency AMRUT 2
Category AMRUT 2
Type of scheme Water Supply
Scheme
Description AMRUT 2.0-Angamaly Muncipality in Ernakulam District-Providing Functional House hold Tap Connections to Angamaly Munciplality , Replacement of damaged distribution lines, providing rider lines, extensions and allied works - Part I
Status On-going
District Ernakulam
Executing Office Aluva PH Dn
AS Amount (Rs) 49610000
AS Number G.O.(Rt)No.2906/2022/LSGD
TS Amount (Rs) 47900000
TS Number WRD/KWA-CE(CR)/EST_TS/1109/2022_5_1_1
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 380000
Capacity in MLD 5.60
Actual Project Completion Date 15 Mar 2024
Coverage 1000 FHTC

Packages

No. Project Name Location View
1 AMRUT-AMRUT 2.0-Angamaly Muncipality Angamaly Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
08 May 2024 361 FHTC Geo Tagged + 430 Nos completed up to meter 1060m of 63mm PVC laying completed,2379.2m of 90mm PVC laying completed,1163.5m of 110mm PVC laying completed,702m of 160mm PVC laying completed. Road restoration work ongoing. GI gap closing, Pipe laying work, Interconnection work are progressing Angamaly AE
07 May 2024 361 FHTC Geo Tagged + 430 Nos completed up to meter 1060m of 63mm PVC laying completed,2379.2m of 90mm PVC laying completed,1163.5m of 110mm PVC laying completed,702m of 160mm PVC laying completed. Road restoration work ongoing. GI gap closing, Pipe laying work, Interconnection work are progressing Angamaly AE
06 May 2024 361 FHTC Geo Tagged + 430 Nos completed up to meter 1060m of 63mm PVC laying completed,2379.2m of 90mm PVC laying completed,1163.5m of 110mm PVC laying completed,702m of 160mm PVC laying completed. Road restoration work ongoing. GI gap closing, Pipe laying work, Interconnection work are progressing Angamaly AE
04 May 2024 277 FHTC Geo Tagged + 510 Nos completed up to meter 1060m of 63mm PVC laying completed,2379.2m of 90mm PVC laying completed,1163.5m of 110mm PVC laying completed,702m of 160mm PVC laying completed. Road restoration work ongoing. GI gap closing, Pipe laying work, Interconnection work are progressing Angamaly AE
03 May 2024 277 FHTC Geo Tagged + 510 Nos completed up to meter 1060m of 63mm PVC laying completed,2379.2m of 90mm PVC laying completed,1163.5m of 110mm PVC laying completed,702m of 160mm PVC laying completed. Road restoration work ongoing. GI gap closing, Pipe laying work, Interconnection work are progressing Angamaly AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 03/07/2023
Scheduled date of Completion of the Project 02 Jan 2024
Expected date of Completion 30/06/2024

Processing Dates

AS Date 24 Nov 2022
TS Date 27 Feb 2023