- Home
- AMRUT 2.0-Angamaly Muncipality
AMRUT 2.0-Angamaly Muncipality
Project |
AMRUT 2.0-Angamaly Muncipality |
Project Code |
EKMAMRUT 2112214147 |
Type |
Main project |
Funding Agency |
AMRUT 2 |
Category |
AMRUT 2 |
Type of scheme |
Water Supply |
Scheme |
|
Description |
AMRUT 2.0-Angamaly Muncipality in Ernakulam District-Providing Functional House hold Tap Connections to Angamaly Munciplality , Replacement of damaged distribution lines, providing rider lines, extensions and allied works - Part I |
Status |
On-going |
District |
Ernakulam |
Executing Office |
Aluva PH Dn |
AS Amount (Rs) |
49610000
|
AS Number |
G.O.(Rt)No.2906/2022/LSGD |
TS Amount (Rs) |
47900000 |
TS Number |
WRD/KWA-CE(CR)/EST_TS/1109/2022_5_1_1 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
380000 |
Capacity in MLD |
5.60 |
Actual Project Completion Date |
15 Mar 2024 |
Coverage |
1000 FHTC |
Packages
No. |
Project Name |
Location |
View |
1 |
AMRUT-AMRUT 2.0-Angamaly Muncipality |
Angamaly Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
08 May 2024 |
361 FHTC Geo Tagged + 430 Nos completed up to meter 1060m of 63mm PVC laying completed,2379.2m of 90mm PVC laying completed,1163.5m of 110mm PVC laying completed,702m of 160mm PVC laying completed. Road restoration work ongoing. GI gap closing, Pipe laying work, Interconnection work are progressing |
Angamaly AE |
|
07 May 2024 |
361 FHTC Geo Tagged + 430 Nos completed up to meter 1060m of 63mm PVC laying completed,2379.2m of 90mm PVC laying completed,1163.5m of 110mm PVC laying completed,702m of 160mm PVC laying completed. Road restoration work ongoing. GI gap closing, Pipe laying work, Interconnection work are progressing |
Angamaly AE |
|
06 May 2024 |
361 FHTC Geo Tagged + 430 Nos completed up to meter 1060m of 63mm PVC laying completed,2379.2m of 90mm PVC laying completed,1163.5m of 110mm PVC laying completed,702m of 160mm PVC laying completed. Road restoration work ongoing. GI gap closing, Pipe laying work, Interconnection work are progressing |
Angamaly AE |
|
04 May 2024 |
277 FHTC Geo Tagged + 510 Nos completed up to meter 1060m of 63mm PVC laying completed,2379.2m of 90mm PVC laying completed,1163.5m of 110mm PVC laying completed,702m of 160mm PVC laying completed. Road restoration work ongoing. GI gap closing, Pipe laying work, Interconnection work are progressing |
Angamaly AE |
|
03 May 2024 |
277 FHTC Geo Tagged + 510 Nos completed up to meter 1060m of 63mm PVC laying completed,2379.2m of 90mm PVC laying completed,1163.5m of 110mm PVC laying completed,702m of 160mm PVC laying completed. Road restoration work ongoing. GI gap closing, Pipe laying work, Interconnection work are progressing |
Angamaly AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
03/07/2023 |
Scheduled date of Completion of the Project |
02 Jan 2024 |
Expected date of Completion |
30/06/2024 |
Processing Dates
AS Date |
24 Nov 2022 |
TS Date |
27 Feb 2023 |