Overall Project Status

Status Date Overall Project Status Project Officer Contact
18 May 2024 361 FHTC Geo Tagged + 430 Nos completed up to meter. 108 m - 400mm DI K9 pipe, 1060m - 63mm PVC, 2379.2m - 90mm PVC , 1163.5m - 110mm PVC, 702m - 160mm PVC laying completed. Road restoration work, GI gap closing and Interconnection works are progressing, Angamaly AE
16 May 2024 361 FHTC Geo Tagged + 430 Nos completed up to meter. 47.82 m - 400mm DI K9 pipe, 1060m - 63mm PVC, 2379.2m - 90mm PVC , 1163.5m - 110mm PVC, 702m - 160mm PVC laying completed. Road restoration work, GI gap closing and Interconnection works are progressing, Angamaly AE
15 May 2024 361 FHTC Geo Tagged + 430 Nos completed up to meter. 38.46 m - 400mm DI K9 pipe, 1060m - 63mm PVC, 2379.2m - 90mm PVC , 1163.5m - 110mm PVC, 702m - 160mm PVC laying completed. Road restoration work, GI gap closing and Interconnection works are progressing, Angamaly AE
14 May 2024 361 FHTC Geo Tagged + 430 Nos completed up to meter 1060m of 63mm PVC laying completed,2379.2m of 90mm PVC laying completed,1163.5m of 110mm PVC laying completed,702m of 160mm PVC laying completed. Road restoration work ongoing. GI gap closing, Pipe laying work, Interconnection work are progressing 400mm DI k9 pipe 12m laying Angamaly AE
13 May 2024 361 FHTC Geo Tagged + 430 Nos completed up to meter 1060m of 63mm PVC laying completed,2379.2m of 90mm PVC laying completed,1163.5m of 110mm PVC laying completed,702m of 160mm PVC laying completed. Road restoration work ongoing. GI gap closing, Pipe laying work, Interconnection work are progressing Angamaly AE
08 May 2024 361 FHTC Geo Tagged + 430 Nos completed up to meter 1060m of 63mm PVC laying completed,2379.2m of 90mm PVC laying completed,1163.5m of 110mm PVC laying completed,702m of 160mm PVC laying completed. Road restoration work ongoing. GI gap closing, Pipe laying work, Interconnection work are progressing Angamaly AE
07 May 2024 361 FHTC Geo Tagged + 430 Nos completed up to meter 1060m of 63mm PVC laying completed,2379.2m of 90mm PVC laying completed,1163.5m of 110mm PVC laying completed,702m of 160mm PVC laying completed. Road restoration work ongoing. GI gap closing, Pipe laying work, Interconnection work are progressing Angamaly AE
06 May 2024 361 FHTC Geo Tagged + 430 Nos completed up to meter 1060m of 63mm PVC laying completed,2379.2m of 90mm PVC laying completed,1163.5m of 110mm PVC laying completed,702m of 160mm PVC laying completed. Road restoration work ongoing. GI gap closing, Pipe laying work, Interconnection work are progressing Angamaly AE
04 May 2024 277 FHTC Geo Tagged + 510 Nos completed up to meter 1060m of 63mm PVC laying completed,2379.2m of 90mm PVC laying completed,1163.5m of 110mm PVC laying completed,702m of 160mm PVC laying completed. Road restoration work ongoing. GI gap closing, Pipe laying work, Interconnection work are progressing Angamaly AE
03 May 2024 277 FHTC Geo Tagged + 510 Nos completed up to meter 1060m of 63mm PVC laying completed,2379.2m of 90mm PVC laying completed,1163.5m of 110mm PVC laying completed,702m of 160mm PVC laying completed. Road restoration work ongoing. GI gap closing, Pipe laying work, Interconnection work are progressing Angamaly AE