AMRUT-AMRUT 2.0-Angamaly Muncipality

Project AMRUT-AMRUT 2.0-Angamaly Muncipality
Project Code EKMAMRUT 2112214147P1
Type Package
Main Project AMRUT 2.0-Angamaly Muncipality
Funding Agency AMRUT 2
Category AMRUT 2
Type of scheme Water Supply
Scheme
Description AMRUT-AMRUT 2.0-Angamaly Muncipality in Ernakulam District-Providing Functional House hold Tap Connections to Angamaly Munciplality , Replacement of damaged distribution lines, providing rider lines, extensions and allied works - Part I-AMRUT 2.0-Angamaly Muncipality in Ernakulam District-Providing Functional House hold Tap Connections to Angamaly Munciplality , Replacement of damaged distribution lines, providing rider lines, extensions and allied works - PHASE-1-General Civil Work
Status On-going
District Ernakulam
Executing Office Angamaly Sn
Agreement Number
Agreement Date
TS Amount (Rs) 47900000
TS Number WRD/KWA-CE(CR)/EST_TS/1109/2022_5_1_1
Technical specification Providing 1000 No. FHTC and allied works
Contractor COCHIN MARINE INDUSTRIES (Mob: 9388961464)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 03/07/2023
Scheduled date of Completion as per agreement 02 Jan 2024
Expected date of Completion 02/06/2024

Processing Dates

TS Date 27 Feb 2023
Estimate Approval 27 Feb 2023
NIT Approval 29 Mar 2023
Tender Closing 31 Mar 2023
Technichal Pre-Qualification 13 Apr 2023
Price bid opening 01 Apr 2023

Approval Dates

Workorder Date 09 Jun 2023
NA 23 Jun 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Angamaly AE
Date: 18/05/2024

Work in progress | 52% Completed

361 FHTC Geo Tagged + 430 Nos completed up to meter. 108 m - 400mm DI K9 pipe, 1060m - 63mm PVC, 2379.2m - 90mm PVC , 1163.5m - 110mm PVC, 702m - 160mm PVC laying completed. Road restoration work, GI gap closing and Interconnection works are progressing, .

Angamaly AE
Date: 16/05/2024

Work in progress | 52% Completed

361 FHTC Geo Tagged + 430 Nos completed up to meter. 47.82 m - 400mm DI K9 pipe, 1060m - 63mm PVC, 2379.2m - 90mm PVC , 1163.5m - 110mm PVC, 702m - 160mm PVC laying completed. Road restoration work, GI gap closing and Interconnection works are progressing, .