Project | AMRUT-AMRUT 2.0-Angamaly Muncipality |
---|---|
Project Code | EKMAMRUT 2112214147P1 |
Type | Package |
Main Project | AMRUT 2.0-Angamaly Muncipality |
Funding Agency | AMRUT 2 |
Category | AMRUT 2 |
Type of scheme | Water Supply |
Scheme | |
Description | AMRUT-AMRUT 2.0-Angamaly Muncipality in Ernakulam District-Providing Functional House hold Tap Connections to Angamaly Munciplality , Replacement of damaged distribution lines, providing rider lines, extensions and allied works - Part I-AMRUT 2.0-Angamaly Muncipality in Ernakulam District-Providing Functional House hold Tap Connections to Angamaly Munciplality , Replacement of damaged distribution lines, providing rider lines, extensions and allied works - PHASE-1-General Civil Work |
Status | On-going |
District | Ernakulam |
Executing Office | Angamaly Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 47900000 |
TS Number | WRD/KWA-CE(CR)/EST_TS/1109/2022_5_1_1 |
Technical specification | Providing 1000 No. FHTC and allied works |
Contractor | COCHIN MARINE INDUSTRIES (Mob: 9388961464) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 03/07/2023 |
---|---|
Scheduled date of Completion as per agreement | 02 Jan 2024 |
Expected date of Completion | 02/06/2024 |
TS Date | 27 Feb 2023 |
---|---|
Estimate Approval | 27 Feb 2023 |
NIT Approval | 29 Mar 2023 |
Tender Closing | 31 Mar 2023 |
Technichal Pre-Qualification | 13 Apr 2023 |
Price bid opening | 01 Apr 2023 |
Workorder Date | 09 Jun 2023 |
---|---|
NA | 23 Jun 2023 |
Angamaly AE |
Date: 18/05/2024 |
Work in progress | 52% Completed
361 FHTC Geo Tagged + 430 Nos completed up to meter. 108 m - 400mm DI K9 pipe, 1060m - 63mm PVC, 2379.2m - 90mm PVC , 1163.5m - 110mm PVC, 702m - 160mm PVC laying completed. Road restoration work, GI gap closing and Interconnection works are progressing, .
Angamaly AE |
Date: 16/05/2024 |
Work in progress | 52% Completed
361 FHTC Geo Tagged + 430 Nos completed up to meter. 47.82 m - 400mm DI K9 pipe, 1060m - 63mm PVC, 2379.2m - 90mm PVC , 1163.5m - 110mm PVC, 702m - 160mm PVC laying completed. Road restoration work, GI gap closing and Interconnection works are progressing, .