Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

DEPOSIT- PROVIDING PUMBING SYSTEM AND PUMBING MAIN FROM INTAKE WELL AT CHAKKAKANAM TO TANK AT NEDUMKANDAM THALUK HOSPITAL

Project DEPOSIT- PROVIDING PUMBING SYSTEM AND PUMBING MAIN FROM INTAKE WELL AT CHAKKAKANAM TO TANK AT NEDUMKANDAM THALUK HOSPITAL
Project Code IDKGOK102213439
Type Main project
Funding Agency GOK
Category Deposit Work
Type of scheme Water Supply
Scheme 4215-01-800-89
Description DEPOSIT- PROVIDING PUMBING SYSTEM AND PUMBING MAIN FROM INTAKE WELL AT CHAKKAKANAM TO TANK AT NEDUMKANDAM THALUK HOSPITAL .
Status Completed
District Idukki
Executing Office Kattappana Project Dn
AS Amount (Rs) 4809000
AS Number
TS Amount (Rs) 4809000
TS Number WRD/KWA-CE(CR)/EST TS /8948/2022 5 _1 _1
Total Bill Submitted (Rs) 2744377
Total Bill Paid (Rs) 2569943
Population Benefitted
Capacity in MLD
Actual Project Completion Date Date is not specified
Coverage

Packages

No. Project Name Location View
1 DEPOSIT- PROVIDING PUMBING SYSTEM AND PUMBING MAIN FROM INTAKE WELL AT CHAKKAKANAM TO TANK AT NEDUMKANDAM THALUK HOSPITAL Project Division Kattapana

Overall Project Status

Status Date Overall Project Status Project Officer Contact
23 May 2023 work is completed. Kattappana AEE 1
22 May 2023 2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing Kattappana AEE 1
17 May 2023 2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing Kattappana AEE 1
12 May 2023 2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing Kattappana AEE 1
09 May 2023 2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing Kattappana AEE 1

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 15/12/2022
Scheduled date of Completion of the Project 14 Mar 2023
Expected date of Completion 31/03/2023

Processing Dates

AS Date 13 Nov 2022
TS Date 08 Nov 2022

Other details

Project Officers View