| Project | DEPOSIT- PROVIDING PUMBING SYSTEM AND PUMBING MAIN FROM INTAKE WELL AT CHAKKAKANAM TO TANK AT NEDUMKANDAM THALUK HOSPITAL |
|---|---|
| Project Code | IDKGOK102213439P1 |
| Type | Package |
| Main Project | DEPOSIT- PROVIDING PUMBING SYSTEM AND PUMBING MAIN FROM INTAKE WELL AT CHAKKAKANAM TO TANK AT NEDUMKANDAM THALUK HOSPITAL |
| Funding Agency | GOK |
| Category | Deposit Work |
| Type of scheme | Water Supply |
| Scheme | 4215-01-800-89 |
| Description | DEPOSIT- PROVIDING PUMBING SYSTEM AND PUMBING MAIN FROM INTAKE WELL AT CHAKKAKANAM TO TANK AT NEDUMKANDAM THALUK HOSPITAL |
| Status | On-going |
| District | Idukki |
| Executing Office | Kattappana Project Dn |
| Agreement Number | |
| Agreement Date | |
| TS Amount (Rs) | 4809000 |
| TS Number | WRD/KWA-CE(CR)/EST TS /8948/2022 5 _1 _1 |
| Technical specification |
Project Progress Status |
Project Progress Status |
| No Status Updated |
| Date of start of Package | 20/01/2023 |
|---|---|
| Scheduled date of Completion as per agreement | 14 Mar 2023 |
| Expected date of Completion | 31/03/2023 |
| TS Date | 08 Nov 2022 |
|---|---|
| Estimate Approval | 08 Nov 2022 |
| Workorder Date | 15 Dec 2022 |
|---|---|
| NA | 15 Dec 2022 |
| Kattappana AEE 1 |
| Date: 25/05/2023 |
Work has been completed | 100% Completed
work is completed. .
| Kattappana AEE 1 |
| Date: 24/05/2023 |
Work in progress | 99% Completed
work is completed. .