| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 23 May 2023 | work is completed. | Kattappana AEE 1 | |
| 22 May 2023 | 2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing | Kattappana AEE 1 | |
| 17 May 2023 | 2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing | Kattappana AEE 1 | |
| 12 May 2023 | 2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing | Kattappana AEE 1 | |
| 09 May 2023 | 2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing | Kattappana AEE 1 | |
| 29 Apr 2023 | 2460m of 100 mm GI Pipe laid work and all other parallel works are completed , trial run and completion work is ongoing. | Kattappana AEE 1 | |
| 15 Apr 2023 | 2460m of 100 mm GI Pipe laid work and all other parallel works are completed . | Kattappana AEE 1 | |
| 13 Apr 2023 | 2428m of 100 mm GI Pipe laid work completed and to do only welding work . | Kattappana AEE 1 | |
| 10 Apr 2023 | 2392 m of 100 mm GI Pipes laid and to do the Welding work at site. | Kattappana AEE 1 | |
| 03 Apr 2023 | 1866 m of 100 mm GI Pipes laid and to do the Welding work at site. Waiting for PWD sanction so no work is going on site. | Kattappana AEE 1 |