Deposit Work - Water Supply Scheme to National Institute of Technology Kozhikode
Project |
Deposit Work - Water Supply Scheme to National Institute of Technology Kozhikode |
Project Code |
CLTDEPO092213688 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
Deposit Work - Water Supply Scheme to National Institute of Technology
Kozhikode |
Status |
On-going |
District |
Kozhikkode |
Executing Office |
Kozhikode Project Dn |
AS Amount (Rs) |
114000000
|
AS Number |
Electronic deposit to the Executive Engineer, Project Division, KWA, Kozhikode. 67148129509 gejocv@nitc.ac.in Water Supply P- C1/22/N022/4576 Success 245417607, 245418009, 245417833 |
TS Amount (Rs) |
99000000 |
TS Number |
WRD/KWA-CE(NR)/EST_TS/5912/2022_5_1_1 |
Total Bill Submitted (Rs) |
15151087 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
|
Capacity in MLD |
3.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
|
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Deposit Work - Water Supply Scheme to National Institute of Technology Kozhikode |
Kozhikode Project Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
14 Feb 2024 |
250mm DI - 9200m supplied, 250mm DI -7811.55 m laid, Laying work in progress. Pump set supplied.
|
Kozhikode Project Dn AE5 |
|
02 Feb 2024 |
250mm DI - 9200m supplied, 250mm DI -7662.55 m laid, Laying work in progress.
|
Kozhikode Project Dn AE5 |
|
29 Jan 2024 |
250mm DI - 9200m supplied, 250mm DI -7552.55 m laid, Laying work in progress.
|
Kozhikode Project Dn AE5 |
|
24 Jan 2024 |
250mm DI - 9200m supplied, 250mm DI -7534.05 m laid, Laying work in progress.
|
Kozhikode Project Dn AE5 |
|
15 Jan 2024 |
250mm DI - 9200m supplied, 250mm DI -7170.55 m laid, Laying work in progress. Road restoration work in progress.
|
Kozhikode Project Dn AE5 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
18/01/2023 |
Scheduled date of Completion of the Project |
04 Jul 2023 |
Expected date of Completion |
15/05/2024 |
Processing Dates
AS Date |
26 Sep 2022 |
TS Date |
21 Oct 2022 |