Project | Deposit Work - Water Supply Scheme to National Institute of Technology Kozhikode |
---|---|
Project Code | CLTDEPO092213688P1 |
Type | Package |
Main Project | Deposit Work - Water Supply Scheme to National Institute of Technology Kozhikode |
Funding Agency | DEPO |
Category | Deposit Work |
Type of scheme | Water Supply |
Scheme | DEPO |
Description | Deposit Work - Water Supply Scheme to National Institute of Technology Kozhikode |
Status | On-going |
District | Kozhikkode |
Executing Office | Kozhikode Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 99000000 |
TS Number | WRD/KWA-CE(NR)/EST_TS/5912/2022_5_1_1 |
Technical specification | Supply erection and commisioning of centrifugal pumpset, Laying clear water pumping main 250mm - 9200m and 200mm-12m |
Contractor | VR7 INFRASTRUCTURES (Mob: 9847552555) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 18/01/2023 |
---|---|
Scheduled date of Completion as per agreement | 04 Jul 2023 |
Expected date of Completion | 31/05/2024 |
TS Date | 21 Oct 2022 |
---|---|
Estimate Approval | 21 Oct 2022 |
Tender Closing | 25 Nov 2022 |
Price bid opening | 28 Nov 2022 |
Workorder Date | 05 Jan 2023 |
---|---|
NA | 18 Jan 2023 |
Kozhikode Project Dn AE4 |
Date: 17/05/2024 |
Work in progress | 95% Completed
250mm DI - 9200m supplied, 250mm DI -7951.05 m laid, Laying work in progress. Pump set supplied. .
Kozhikode Project Dn AE4 |
Date: 16/05/2024 |
Work in progress | 95% Completed
250mm DI - 9200m supplied, 250mm DI -7951.05 m laid, Laying work in progress. Pump set supplied. .