Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
14 Feb 2024 | 250mm DI - 9200m supplied, 250mm DI -7811.55 m laid, Laying work in progress. Pump set supplied. | Kozhikode Project Dn AE5 | |
02 Feb 2024 | 250mm DI - 9200m supplied, 250mm DI -7662.55 m laid, Laying work in progress. | Kozhikode Project Dn AE5 | |
29 Jan 2024 | 250mm DI - 9200m supplied, 250mm DI -7552.55 m laid, Laying work in progress. | Kozhikode Project Dn AE5 | |
24 Jan 2024 | 250mm DI - 9200m supplied, 250mm DI -7534.05 m laid, Laying work in progress. | Kozhikode Project Dn AE5 | |
15 Jan 2024 | 250mm DI - 9200m supplied, 250mm DI -7170.55 m laid, Laying work in progress. Road restoration work in progress. | Kozhikode Project Dn AE5 | |
08 Jan 2024 | 250mm DI - 9200m supplied, 250mm DI -7055.05 m laid, Laying work in progress. | Kozhikode Project Dn AE5 | |
24 Dec 2023 | 250mm DI - 9200m supplied, 250mm DI -6669.65 m laid, Laying work in progress. | Kozhikode Project Dn AE5 | |
15 Dec 2023 | 250mm DI - 9200m supplied, 250mm DI -6307.65m laid, Laying work in progress. | Kozhikode Project Dn AE5 | |
09 Dec 2023 | 250mm DI - 9200m supplied, 250mm DI -6076.15 m laid, Laying work in progress. | Kozhikode Project Dn AE5 | |
07 Dec 2023 | 250mm DI - 9200m supplied, 250mm DI -5996.65 m laid, Laying work in progress. | Kozhikode Project Dn AE5 |