AMRUT-AMRUT 2.0 - Pipe line extension/replacement and providing FHTCs in C ZONE-AMRUT 2.0 - WSS To Thalassery Municipality - Pipe Line Extension/Replacement And Provding FHTCs In Thalassery Municipality - C Zone-Pipeline Work

Project AMRUT-AMRUT 2.0 - Pipe line extension/replacement and providing FHTCs in C ZONE-AMRUT 2.0 - WSS To Thalassery Municipality - Pipe Line Extension/Replacement And Provding FHTCs In Thalassery Municipality - C Zone-Pipeline Work
Project Code KNRAMRUT 2112214162P1
Type Package
Main Project Pipe line extension/replacement and providing FHTCs in C ZONE-AMRUT 2.0 - WSS To Thalassery Municipality - Pipe Line Extension/Replacement And Provding FHTCs In Thalassery Municipality - C Zone-Pipeline Work
Funding Agency AMRUT 2
Category AMRUT 2
Type of scheme Water Supply
Scheme
Description AMRUT-AMRUT 2.0 - Pipe line extension/replacement and providing FHTCs in C ZONE-AMRUT 2.0 - WSS To Thalassery Municipality - Pipe Line Extension/Replacement And Provding FHTCs In Thalassery Municipality - C Zone-Pipeline Work
Status On-going
District Kannur
Executing Office Thalassery PH Sn
Agreement Number
Agreement Date
TS Amount (Rs) 62030000
TS Number 17439/2022-2023
Technical specification 1315 FHTCS and 18068 m of pipeline proposed.

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 13/11/2023
Scheduled date of Completion as per agreement 12 Jul 2024
Expected date of Completion 31/12/2024

Processing Dates

TS Date 25 Mar 2023
Estimate Approval 25 Mar 2023
NIT Approval 25 Mar 2023
Price bid opening 03 Nov 2024

Approval Dates

Workorder Date 03 Nov 2024
NA 03 Nov 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Thalassery PH Sn AE
Date: 27/06/2025

Work in progress | 75% Completed

17154 m of pipeline laid and FHTC -355 HTC -395 are given. Work in progress.

Thalassery PH Sn AE
Date: 17/06/2025

Work in progress | 75% Completed

17154 m of pipeline laid and FHTC -350 HTC -390 are given. Work in progress.