Project | AMRUT-AMRUT 2.0 - Pipe line extension/replacement and providing FHTCs in C ZONE-AMRUT 2.0 - WSS To Thalassery Municipality - Pipe Line Extension/Replacement And Provding FHTCs In Thalassery Municipality - C Zone-Pipeline Work |
---|---|
Project Code | KNRAMRUT 2112214162P1 |
Type | Package |
Main Project | Pipe line extension/replacement and providing FHTCs in C ZONE-AMRUT 2.0 - WSS To Thalassery Municipality - Pipe Line Extension/Replacement And Provding FHTCs In Thalassery Municipality - C Zone-Pipeline Work |
Funding Agency | AMRUT 2 |
Category | AMRUT 2 |
Type of scheme | Water Supply |
Scheme | |
Description | AMRUT-AMRUT 2.0 - Pipe line extension/replacement and providing FHTCs in C ZONE-AMRUT 2.0 - WSS To Thalassery Municipality - Pipe Line Extension/Replacement And Provding FHTCs In Thalassery Municipality - C Zone-Pipeline Work |
Status | On-going |
District | Kannur |
Executing Office | Thalassery PH Sn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 62030000 |
TS Number | 17439/2022-2023 |
Technical specification | 1315 FHTCS and 18068 m of pipeline proposed. |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 13/11/2023 |
---|---|
Scheduled date of Completion as per agreement | 12 Jul 2024 |
Expected date of Completion | 31/12/2024 |
TS Date | 25 Mar 2023 |
---|---|
Estimate Approval | 25 Mar 2023 |
NIT Approval | 25 Mar 2023 |
Price bid opening | 03 Nov 2024 |
Workorder Date | 03 Nov 2024 |
---|---|
NA | 03 Nov 2023 |
Thalassery PH Sn AE |
Date: 27/06/2025 |
Work in progress | 75% Completed
17154 m of pipeline laid and FHTC -355 HTC -395 are given. Work in progress.
Thalassery PH Sn AE |
Date: 17/06/2025 |
Work in progress | 75% Completed
17154 m of pipeline laid and FHTC -350 HTC -390 are given. Work in progress.