DEPOSIT WORK - KRISHNAPURAM GRAMA PANCHAYAT 2019-20 :- PROJECT NO.185/2020 - PIPE LINE EXTENSION FROM ERANDACKAL JN. TO THIRUVONAM JN. IN WARD NO. 17 OF KRISHNAPURAM GRAMA PANCHAYAT.

Project DEPOSIT WORK - KRISHNAPURAM GRAMA PANCHAYAT 2019-20 :- PROJECT NO.185/2020 - PIPE LINE EXTENSION FROM ERANDACKAL JN. TO THIRUVONAM JN. IN WARD NO. 17 OF KRISHNAPURAM GRAMA PANCHAYAT.
Project Code ALPDEPO11208704
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description DEPOSIT WORK - KRISHNAPURAM GRAMA PANCHAYAT 2019-20 :- PROJECT NO.185/2020 - PIPE LINE EXTENSION FROM ERANDACKAL JN. TO THIRUVONAM JN. IN WARD NO. 17 OF KRISHNAPURAM GRAMA PANCHAYAT.
Status Completed
District Alappuzha
Executing Office Kayamkulam PH Sn
AS Amount (Rs) 100000
AS Number 1128 of 2020-2021 dated 10-11-2020
TS Amount (Rs) 92700
TS Number TS/2020-2021/2020/6009 Dated: 07-12-2020
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 300
Capacity in MLD 1.00
Actual Project Completion Date 11 Feb 2022
Coverage FROM ERANDACKAL JN. TO THIRUVONAM JN. IN WARD NO. 17 OF KRISHNAPURAM GRAMA PANCHAYAT.
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 DEPOSIT WORK - KRISHNAPURAM GRAMA PANCHAYAT 2019-20 :- PROJECT NO.185/2020 - PIPE LINE EXTENSION FROM ERANDACKAL JN. TO THIRUVONAM JN. IN WARD NO. 17 OF KRISHNAPURAM GRAMA PANCHAYAT. Kayamkulam PH Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
27 Mar 2022 Final bill submitted to subdivision Kayamkulam AE
27 Feb 2022 work completed Kayamkulam AE
20 Feb 2022 Pipe line laying and interconnection completed Kayamkulam AE
15 Feb 2022 Pipe line laying and interconnection completed Kayamkulam AE
11 Feb 2022 Work in progress Kayamkulam AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 15/01/2022
Scheduled date of Completion of the Project 12 Feb 2022
Expected date of Completion 28/02/2022

Processing Dates

AS Date 10 Nov 2020
TS Date 07 Dec 2020

Other details

Project Officers View