Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
27 Mar 2022 | Final bill submitted to subdivision | Kayamkulam AE | |
27 Feb 2022 | work completed | Kayamkulam AE | |
20 Feb 2022 | Pipe line laying and interconnection completed | Kayamkulam AE | |
15 Feb 2022 | Pipe line laying and interconnection completed | Kayamkulam AE | |
11 Feb 2022 | Work in progress | Kayamkulam AE | |
09 Feb 2022 | Work Progressing | Kayamkulam AE |