DEPOSIT WORK - KRISHNAPURAM GRAMA PANCHAYAT 2019-20 :- PROJECT NO.185/2020 - PIPE LINE EXTENSION FROM ERANDACKAL JN. TO THIRUVONAM JN. IN WARD NO. 17 OF KRISHNAPURAM GRAMA PANCHAYAT.

Project DEPOSIT WORK - KRISHNAPURAM GRAMA PANCHAYAT 2019-20 :- PROJECT NO.185/2020 - PIPE LINE EXTENSION FROM ERANDACKAL JN. TO THIRUVONAM JN. IN WARD NO. 17 OF KRISHNAPURAM GRAMA PANCHAYAT.
Project Code ALPDEPO11208704P1
Type Package
Main Project DEPOSIT WORK - KRISHNAPURAM GRAMA PANCHAYAT 2019-20 :- PROJECT NO.185/2020 - PIPE LINE EXTENSION FROM ERANDACKAL JN. TO THIRUVONAM JN. IN WARD NO. 17 OF KRISHNAPURAM GRAMA PANCHAYAT.
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description DEPOSIT WORK - KRISHNAPURAM GRAMA PANCHAYAT 2019-20 :- PROJECT NO.185/2020 - PIPE LINE EXTENSION FROM ERANDACKAL JN. TO THIRUVONAM JN. IN WARD NO. 17 OF KRISHNAPURAM GRAMA PANCHAYAT.
Status On-going
District Alappuzha
Executing Office Kayamkulam PH Sn
Agreement Number
Agreement Date
TS Amount (Rs) 92700
TS Number TS/2020-2021/2020/6009 Dated: 07-12-2020
Technical specification PIPE LINE EXTENSION FROM ERANDACKAL JN. TO THIRUVONAM JN. IN WARD NO. 17 OF KRISHNAPURAM GRAMA PANCHAYAT.

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 15/01/2022
Scheduled date of Completion as per agreement 12 Feb 2022
Expected date of Completion 28/02/2022

Processing Dates

TS Date 07 Dec 2020
Estimate Approval 07 Dec 2020
NIT Approval 07 Dec 2020
Tender Closing 09 Feb 2021
Technichal Pre-Qualification 12 Feb 2021
Price bid opening 12 Feb 2021

Approval Dates

Workorder Date 15 Jan 2022
NA 14 Jan 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Kayamkulam AE
Date: 27/02/2022

Work has been completed | 100% Completed

work completed.

Kayamkulam AE
Date: 20/02/2022

Work in progress | 80% Completed